how much quantity of cement and sand required for
construction of 10 cum brick work( Brick size
3"*4"*9"(Standard size ) an d for 10 cum construction of SSM
(Size stone masonary) with Cm 1:6 for both.

Answers were Sorted based on User's Feedback



how much quantity of cement and sand required for construction of 10 cum brick work( Brick size 3..

Answer / b.s.dev

Let the size of brick be 230mm x 115mm x 75mm
Vol. of brick( w/o mortar) = 0.00198 cum.
Thk. of mortar be 12mm.
vol. of brick with mortar = 242mm x 127mm x 87mm
= 0.00267 cum.
No. of bricks in 1 cum. with mortar = 1/0.00267
= 373.99
Say = 374 bricks.
Cement Mortar required = 1-( 374 x 0.00198)cum.
= 0.259 cum.
Say 0.26 cum

Add 15% for frog filling and wastage while execution.
Vol. of wet mortar = 0.299 cum.
Vol. of dry mortar( increase by 30% ) = 0.388 cum.

For CM of 1:6

Qty. of cement = 1/7 x (1440 x 0.388)
= 0.055 cum.
Qty. of sand = 0.055 x 6
= 0.330 cum.

Is This Answer Correct ?    188 Yes 60 No

how much quantity of cement and sand required for construction of 10 cum brick work( Brick size 3..

Answer / ar. g.s. rehal

Let the size of brick be 230mm x 115mm x 75mm
Vol. of brick( w/o mortar) = 0.00198 cum.
Thk. of mortar be 12mm.
vol. of brick with mortar = 242mm x 127mm x 87mm
= 0.00267 cum.
No. of bricks in 1 cum. with mortar = 1/0.00267
= 373.99
Say = 374 bricks.
volume of 374 bricks= 374 x 0.00198 = 0.74052cum
Cement Mortar required for 1cum = 1 - 0.74052cum.
= 0.259 cum.
Say 0.26 cum

Add 15% for frog filling and wastage while execution.
.26 x 15/100 = 0.299 cum
Vol. of wet mortar = 0.299 cum.
Vol. of dry mortar( increase by 30% ) 0.299 x 30/100 =0.0897
0.299 + 0.0897 = 0.388 cum.

For CM of 1:6 (1 + 6 = 7)

Qty. of cement for 1cum = 1/7 x 0.388
= 0.055 cum.
Qty. of sand for 1cum = 0.055 x 6
= 0.330 cum.

Qty. of cement for 10cum =10 x 0.055
=0.55 cum.
Qty. of sand for 10cum = 10 x 0.330
= 3.30 cum.

Is This Answer Correct ?    89 Yes 24 No

how much quantity of cement and sand required for construction of 10 cum brick work( Brick size 3..

Answer / uday kiran

The size of brick be 230mm x 115mm x 75mm
Vol.of brick( w/o mortar) = 0.00198 cum.
Thk.of mortar be 12mm.
vol.of brick with mortar = 242mm x 127mm x 87mm = 0.00267 cum.
No.of bricks in 1 cum. with mortar = 1/0.00267 = 373.99
Say = 374 bricks.
Cement Mortar required = 1-(374 x 0.00198) cum= 0.259 cum.
Say 0.26 cum
Add 15% for frog filling and wastage while execution.
Vol. of wet mortar = 0.299 cum.
Vol. of dry mortar (increase by 30%) = 0.388 cum.
For CM of 1:6
Qty. of cement = 1/7 x (1440 x 0.388) = 0.055 cum.
Qty. of sand = 0.055 x 6 = 0.330 cum.

Is This Answer Correct ?    36 Yes 11 No

how much quantity of cement and sand required for construction of 10 cum brick work( Brick size 3..

Answer / jocky

mortar required for 10 cu.m brick work

Dry mortar = 30% of brick work = 3 cu.m

one part of cement=3cu.m/sum of proportion

(3/1+6)=0.428cu.m

cement required in bags...0.428/vol. of one bag of cement

(0.428/0.035) =12.23 bags ..take 13 bags of cement

sand = 0.428*6= 2.57 cu.m

Is This Answer Correct ?    24 Yes 10 No

how much quantity of cement and sand required for construction of 10 cum brick work( Brick size 3..

Answer / sudhir

see CPWD ANALYSIS
480 BRICKS PER CUM I/C WASTAGE
1.24 BAGS CEMENT/CUM I/C WASTAGE
1.24*.035*6 = WILL BE THE QTY OF C.SAND REQD/ PER CUM

Is This Answer Correct ?    28 Yes 15 No

how much quantity of cement and sand required for construction of 10 cum brick work( Brick size 3..

Answer / bhupendra potpose

Consumption & Rate analysis Brick Masnory 230mm 1:6
Superstructure With scaffolding

Providing and placing brick work 230mm 1:6 Superstructure
With scaffolding
1.3Ref: use 1..3 standard
Proportion of materials
Cement 1
Sand 6
Total 7
Std constant(1.5) / Total of proporttion(4)
0.186
1) Required volume of cement for 1 cum.

1 Proportion of cement 0.19
Add wastage(2.50%) 0.005
Vol of cement for 1 cum 0.190
0.035 is cum of per 50kg of bags 5.44.

As per standard we assumed that in 1cum of brick work ,the
quantity of mortor (Cement & Sand )is consider in
quantity. (24%) 1.28
Cost of cement per bags 325
Total cost of 1.34 bags 415.39

2) Required volume of Sand for 1 cum

2 Proportionof Sand 1.114
Add wastage(2.50%) 0.028
Vol of Sand for 1 cum 1.142
As per standard we assumed that in 1cum of brick work ,
the quantity of mortor (Cement & Sand )is consider in
quantity.(24%) 0.268
Cost of sand per brass 875
Total cost of 0.284 cum sand 234.85


3)Required brick for 1 cum of size 230x115x75mm

Actual Vol of one bricks is 0.00198cum,&
10 gap Allaround is become 0.00255
Nos of bricks in 1cum0.00255 1 392.16
Add wastage(10.00%) 39.22
Total Required brick for
1 cum 431.37
Cost of bricks 5.00
Total cost of brick 2156.86

A)Total material cost (1+2+3)
2807.10

4)Cost for Manpower ,Mixing ,Shifting ,
placing etc, Rs 15 / sft-Mumbai, 529.80

5) Cost for screeing,
cleaning ,of sand (10%) 333.69
6) Cost for Tools ,
Safety, curing etc(5%) 183.53
B) Cost of labour on
total material cost (4+5+6)
1047.02

C) Cost of Material & labour (A+B) 3854.12

5)Add over head(5%) 192.71
6)Add profit on(15%) 607.02


D- Total of (C+5+6),Over head & profit cost
P/A P230mm,1:6 Per Sqm. 4653.85
If the brick work is required to .


convert into Sqmt
1) for 230mm ; 0.23 1070.39
2) for 115mm ; 0.115 535.19

Is This Answer Correct ?    11 Yes 2 No

how much quantity of cement and sand required for construction of 10 cum brick work( Brick size 3..

Answer / arvind vyas

The size of brick be 230mm x 115mm x 75mm
Vol.of brick( w/o mortar) = 0.00198 cum.
Thk.of mortar be 12mm.
vol.of brick with mortar = 242mm x 127mm x 87mm = 0.00267
cum.
No.of bricks in 1 cum. with mortar = 1/0.00267 = 373.99
Say = 374 bricks.
Cement Mortar required = 1-(374 x 0.00198) cum= 0.259 cum.
Say 0.26 cum
Add 15% for frog filling and wastage while execution.
Vol. of wet mortar = 0.299 cum.
Vol. of dry mortar (increase by 30%) = 0.388 cum.
For CM of 1:6
Qty. of cement = 1/7 x (1440 x 0.388) = 0.055 cum.
Qty. of sand = 0.055 x 6 = 0.330 cum

Is This Answer Correct ?    8 Yes 4 No

how much quantity of cement and sand required for construction of 10 cum brick work( Brick size 3..

Answer / karan bagga

lets the take size of brick is .230*.115*.075. now calculate
the quantity for 10 cum.

Area of one brick without mortar -0.00198375 Cum
No of brick in 10 cum= 10/0.00198375 (Area of bricks).
=5041 nos of bricks.

now calc. the bricks quantity in 10 cum with mortar.

lets take the mortar used 10mm in brickwork then
size of brick will be taken with mortar is =.240*.125*.085=
0.00255 (Area of one brick with mortar).

now in 10 cum brickwork no of bricks calculated with mortar
is=10/0.00255 =3922 nos

calculate the mortar in cum= bricks without mortar- bricks
with mortar= 5041-3922=1119 nos
Now area of brick without mortar is .230*.115*.075*1119=2.22cum

now 15% for frog filling and wastage taken in acc.

=2.22+2.22*15/100=2.55 cum

Dry volume is the 1/3rd of wet volume of mortar=
2.55+2.55/1/3=3.40 cum.

now the ratio is 1:6=7

3.40*14%=.486 cum cement
3.40*86%= 2.92 Cum Sand

=.486/.0347= 14.01 bags/10 Cum
= 14.01*6=84.06 Bags/10 Cum

Is This Answer Correct ?    5 Yes 3 No

how much quantity of cement and sand required for construction of 10 cum brick work( Brick size 3..

Answer / muthu kumaran

No of bricks = 500 [5(Stredger face with 10mm CM)*10(Header face with 10mm CM)*10(Header face with 10mm CM)]
Volume of mortar required = 1-500*0.19*0.09*0.09
= 0.2305 cubic metre
Cement required for 1:6 = (0.2305*1440)/7
= 47.41 Kg (Approx. 48 Kg)
(Density of cement 1440 Kg/cu.m)
Sand required = 284.5 Kg (Approx. 288 Kg)

Is This Answer Correct ?    9 Yes 13 No

how much quantity of cement and sand required for construction of 10 cum brick work( Brick size 3..

Answer / sjtbehera

you are given 3”x4”x9” standard size of bricks
After placing mortar it became- 4”x5”x10” =
10.16cmx12.7cmx25.4cm
No of bricks are required=
10/.106x.127x.254=3069 nos
The size of brick without mortar= 3”x4”x9”=
7.62cmx10.1cmx22.8cm
Then net mortar required =10-(3069*.076*.101*.228)
= 4.62cum
Due to frog filling, brick bonding course and
wastage add 15%
Volume of wet mortar= 4.62+4.62x15%=5.30cum
When dry increase this qty. by 1/3rd=
5.30+5.30x1/3=7.06cum
Ratio is =1+6=7 cement = 7.06/7= 1.06 = 29 bags
Sand= 7.06*6= 42.36cum

Is This Answer Correct ?    47 Yes 54 No

Post New Answer

More Civil Engineering Interview Questions

load combinations how many types for staad design purpose?

0 Answers   Descon,


 rcc floor to floor  4m. in column reinforcement where we provide lap in exact location.     

0 Answers   Jain Group,


how much binding wire required per tonne slab beam columns

5 Answers   GMR,


what is a exact size of a cube?

7 Answers   Green Concretex,


how to calculate concrete pouring of foundation

2 Answers  






How to build the floor to ceiling bookcase?

0 Answers  


what is mean by k150

2 Answers   Kuwait Oil Company,


What is The meaning Of Auto cad And Also Define What Is Drawing According To You

14 Answers   MNC,


How to calculate measurement box size for M25 grade cement?

3 Answers   Perunding Omega PMC,


consumption of cement in p.c.c. a. mix. 1:1:2 b. mix. 1:1.5:3 c. mix. 1:2:4 d. mix. 1:3:6 e. mix. 1:4:8

2 Answers   MSPL,


How cracks in concrete can be avoided?

0 Answers  


1. if only 1 slab of a floor get sagged, how could be it repaired? 2. if any footing gives the cube result, after 28 days less than 16 n/mm2 in spite of 20 n/mm2 what are the remedies ?

3 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4452)
  • Electrical Engineering Interview Questions Electrical Engineering (16638)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)