how much quantity of cement and sand required for
construction of 10 cum brick work( Brick size
3"*4"*9"(Standard size ) an d for 10 cum construction of SSM
(Size stone masonary) with Cm 1:6 for both.

Answer Posted / muthu kumaran

No of bricks = 500 [5(Stredger face with 10mm CM)*10(Header face with 10mm CM)*10(Header face with 10mm CM)]
Volume of mortar required = 1-500*0.19*0.09*0.09
= 0.2305 cubic metre
Cement required for 1:6 = (0.2305*1440)/7
= 47.41 Kg (Approx. 48 Kg)
(Density of cement 1440 Kg/cu.m)
Sand required = 284.5 Kg (Approx. 288 Kg)

Is This Answer Correct ?    9 Yes 13 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Explain the difference between slab and beam?

669


What are the uses of groynes?

682


Define absolute co-ordinates?

755


a sewer which receives the discharge of no. of house sewer is called house sewer lateral sewer intrcepting sewer sub-main sewer

2031


what is modular brick and it size

1175






Pile height is 4.3m. 2nos. under reammer. bulb nose is 75mm and height is 400mm. pile dia is 375mm and overall dia 940mm.pls. help to calculate concrete in pile and bulbs separately. What is formula for bulb volume calculation ?

1285


What is the substitute of Mastic Asphalt?

6961


the water is flowing through a velocity of 1.5m/s in a pipe of length 2500m and dia 500mm. at the end of pipe a valve is provided. find rise in pressure 1. if the valve is closed in 5 seconds. 2. if the valve is closed instantaneously. take value of c = 1460m/s, pipe to be rigid and bulk modulus of water - 19.692x10' n/sqcm

1890


how to calculate the density for high density concrete ? or is it same as the density of RC?

1883


to minimize budget cost of building , what can i do

1671


sir please send me campus placement questions in civil engineering

3133


What is demising walls?

695


cement and sand required for one block of size 0.23*0.15*0.46

1389


what is the design procedure for building

1769


Why should appointment store person for project ? what is the benefits for company ?

621