how much quantity of cement and sand required for
construction of 10 cum brick work( Brick size
3"*4"*9"(Standard size ) an d for 10 cum construction of SSM
(Size stone masonary) with Cm 1:6 for both.
Answer Posted / bhupendra potpose
Consumption & Rate analysis Brick Masnory 230mm 1:6
Superstructure With scaffolding
Providing and placing brick work 230mm 1:6 Superstructure
With scaffolding
1.3Ref: use 1..3 standard
Proportion of materials
Cement 1
Sand 6
Total 7
Std constant(1.5) / Total of proporttion(4)
0.186
1) Required volume of cement for 1 cum.
1 Proportion of cement 0.19
Add wastage(2.50%) 0.005
Vol of cement for 1 cum 0.190
0.035 is cum of per 50kg of bags 5.44.
As per standard we assumed that in 1cum of brick work ,the
quantity of mortor (Cement & Sand )is consider in
quantity. (24%) 1.28
Cost of cement per bags 325
Total cost of 1.34 bags 415.39
2) Required volume of Sand for 1 cum
2 Proportionof Sand 1.114
Add wastage(2.50%) 0.028
Vol of Sand for 1 cum 1.142
As per standard we assumed that in 1cum of brick work ,
the quantity of mortor (Cement & Sand )is consider in
quantity.(24%) 0.268
Cost of sand per brass 875
Total cost of 0.284 cum sand 234.85
3)Required brick for 1 cum of size 230x115x75mm
Actual Vol of one bricks is 0.00198cum,&
10 gap Allaround is become 0.00255
Nos of bricks in 1cum0.00255 1 392.16
Add wastage(10.00%) 39.22
Total Required brick for
1 cum 431.37
Cost of bricks 5.00
Total cost of brick 2156.86
A)Total material cost (1+2+3)
2807.10
4)Cost for Manpower ,Mixing ,Shifting ,
placing etc, Rs 15 / sft-Mumbai, 529.80
5) Cost for screeing,
cleaning ,of sand (10%) 333.69
6) Cost for Tools ,
Safety, curing etc(5%) 183.53
B) Cost of labour on
total material cost (4+5+6)
1047.02
C) Cost of Material & labour (A+B) 3854.12
5)Add over head(5%) 192.71
6)Add profit on(15%) 607.02
D- Total of (C+5+6),Over head & profit cost
P/A P230mm,1:6 Per Sqm. 4653.85
If the brick work is required to .
convert into Sqmt
1) for 230mm ; 0.23 1070.39
2) for 115mm ; 0.115 535.19
| Is This Answer Correct ? | 11 Yes | 2 No |
Post New Answer View All Answers
how to calibrate the RM 800
how to Concrete cubes testing curing time 7 days casting date 24.05.17 testing date ?
What is the maximum crushing load in Kg & crushing strength in N/mm2 for M25 & M 15 Grade concrete
How you can use different dimension tools in cad? What are the different dimensions available?
is there any codal provision for soil cousion over the Hume pipe of Dia 1.2 m.
How to improve the strength of fly ash bricks to avoid corner damge? How to get the color lighter similar to normal concrete blocks/
What the advantages and disadvantage of using 90mm and 100mm bricks for a wall of a house? Thanks for any input.
What is absolute coordinates?
kindly mail me by attaching files , formats for quality checks of common building materials like cement , concrete , bricks , sand and aggregates plz send my email id- VMANDAL91@gmail.com
what is the ingredient value of 40mm and 20mm aggregates?
What is the cost difference between site mix and ready mix concrete per cubic meter
what is the 0 value in quantity surveying
in plate load test what is the thickness of plate 20mm 5mm 50mm none
What is rolling stock
In cement concrete how to check a quality of material also proportion of material at site ?