Consumption & Rate analysis Brick Masnory 230mm 1:6
Superstructure With scaffolding
Providing and placing brick work 230mm 1:6 Superstructure
With scaffolding
1.3Ref: use 1..3 standard
Proportion of materials
Cement 1
Sand 6
Total 7
Std constant(1.5) / Total of proporttion(4)
0.186
1) Required volume of cement for 1 cum.
1 Proportion of cement 0.19
Add wastage(2.50%) 0.005
Vol of cement for 1 cum 0.190
0.035 is cum of per 50kg of bags 5.44.
As per standard we assumed that in 1cum of brick work ,the
quantity of mortor (Cement & Sand )is consider in
quantity. (24%) 1.28
Cost of cement per bags 325
Total cost of 1.34 bags 415.39
2) Required volume of Sand for 1 cum
2 Proportionof Sand 1.114
Add wastage(2.50%) 0.028
Vol of Sand for 1 cum 1.142
As per standard we assumed that in 1cum of brick work ,
the quantity of mortor (Cement & Sand )is consider in
quantity.(24%) 0.268
Cost of sand per brass 875
Total cost of 0.284 cum sand 234.85
3)Required brick for 1 cum of size 230x115x75mm
Actual Vol of one bricks is 0.00198cum,&
10 gap Allaround is become 0.00255
Nos of bricks in 1cum0.00255 1 392.16
Add wastage(10.00%) 39.22
Total Required brick for
1 cum 431.37
Cost of bricks 5.00
Total cost of brick 2156.86
A)Total material cost (1+2+3)
2807.10
4)Cost for Manpower ,Mixing ,Shifting ,
placing etc, Rs 15 / sft-Mumbai, 529.80
5) Cost for screeing,
cleaning ,of sand (10%) 333.69
6) Cost for Tools ,
Safety, curing etc(5%) 183.53
B) Cost of labour on
total material cost (4+5+6)
1047.02
C) Cost of Material & labour (A+B) 3854.12
5)Add over head(5%) 192.71
6)Add profit on(15%) 607.02
D- Total of (C+5+6),Over head & profit cost
P/A P230mm,1:6 Per Sqm. 4653.85
If the brick work is required to .
convert into Sqmt
1) for 230mm ; 0.23 1070.39
2) for 115mm ; 0.115 535.19
| Is This Answer Correct ? | 11 Yes | 2 No |
Post New Answer View All Answers
Calculate the maximum allowable speed on a horizontal curve of radius 350m if the maximum allowable values of the lateral coefficient of friction are 0.14 and the rate of superelevation is 0.08.
Can anyone suggest how to determine scheduling of reinforcement of floor beams from Staad model,other than clicking each beam respectively 7 noting down the values ?
What is missing report and how to prepare
How do you determine specific gravity of cement?
As we know that steel is a tension member but why we are using STRUCTURE STEEL as a COLUMN (Without concrete) where column is a compression member and compression strength of steel is very low
For the symmetrical continuous beam shown in figure, Prestressed with a force P = 1500 KN along parabolic curve as shown, compute the extreme fiber stresses over the central support for the uniformly distributed load of 24 kn/m. Use load balancing method.
How much of fly ash is allowable in Portland cement and what is the disadvantage when the level of fly ash is increased?
Explain why concrete barriers have curved surface profiles?
Which is the latest version of solidsworks?
what is E
Actually i am confused that how to calculate the bending moment for a semi-circular beam and curved slab.If any one have a good idea about the matter,please give the answer with a suitable example. Thank you......
flow of fluid takes place viscosity compressibilityu surface tension deformation under shear force
what is polity
how can i calculate cement in brickwork
how to preaper for interview wat they asked in interview give me idea