how much quantity of cement and sand required for
construction of 10 cum brick work( Brick size
3"*4"*9"(Standard size ) an d for 10 cum construction of SSM
(Size stone masonary) with Cm 1:6 for both.
Answer Posted / bhupendra potpose
Consumption & Rate analysis Brick Masnory 230mm 1:6
Superstructure With scaffolding
Providing and placing brick work 230mm 1:6 Superstructure
With scaffolding
1.3Ref: use 1..3 standard
Proportion of materials
Cement 1
Sand 6
Total 7
Std constant(1.5) / Total of proporttion(4)
0.186
1) Required volume of cement for 1 cum.
1 Proportion of cement 0.19
Add wastage(2.50%) 0.005
Vol of cement for 1 cum 0.190
0.035 is cum of per 50kg of bags 5.44.
As per standard we assumed that in 1cum of brick work ,the
quantity of mortor (Cement & Sand )is consider in
quantity. (24%) 1.28
Cost of cement per bags 325
Total cost of 1.34 bags 415.39
2) Required volume of Sand for 1 cum
2 Proportionof Sand 1.114
Add wastage(2.50%) 0.028
Vol of Sand for 1 cum 1.142
As per standard we assumed that in 1cum of brick work ,
the quantity of mortor (Cement & Sand )is consider in
quantity.(24%) 0.268
Cost of sand per brass 875
Total cost of 0.284 cum sand 234.85
3)Required brick for 1 cum of size 230x115x75mm
Actual Vol of one bricks is 0.00198cum,&
10 gap Allaround is become 0.00255
Nos of bricks in 1cum0.00255 1 392.16
Add wastage(10.00%) 39.22
Total Required brick for
1 cum 431.37
Cost of bricks 5.00
Total cost of brick 2156.86
A)Total material cost (1+2+3)
2807.10
4)Cost for Manpower ,Mixing ,Shifting ,
placing etc, Rs 15 / sft-Mumbai, 529.80
5) Cost for screeing,
cleaning ,of sand (10%) 333.69
6) Cost for Tools ,
Safety, curing etc(5%) 183.53
B) Cost of labour on
total material cost (4+5+6)
1047.02
C) Cost of Material & labour (A+B) 3854.12
5)Add over head(5%) 192.71
6)Add profit on(15%) 607.02
D- Total of (C+5+6),Over head & profit cost
P/A P230mm,1:6 Per Sqm. 4653.85
If the brick work is required to .
convert into Sqmt
1) for 230mm ; 0.23 1070.39
2) for 115mm ; 0.115 535.19
Is This Answer Correct ? | 11 Yes | 2 No |
Post New Answer View All Answers
what is the max. and mim. height of vertical post in informatry sign board which is used in highway projects.
What is the tensile strength of marble?
how to diffenentiate the fixed beam and simply supported beam in the execution while reading the drawing and how the reinforcement detail will be differ for the above.
What is costing in 100squre feet bricks
what do you mean by yeild stress of a material? What will happen when hit is given to cement?
what is the name of shuttering oil used in oman
Differentiate orthographic and isometric projections?
What is meant by cartesian coordinate system?
In the different classes or grades of concrete, what is the difference between C20, M20 B20. what are the letters C, M, and B stands for.
What is Time period of a building and its relation with frequency ?
What is high adherence steel bar? I have a general specification which refers to High Adherence steel bars, coils and meshes to BS EN 10080 and BS 4449 or BS 4483. Is this just general re-bar or is there something different about it? The spec originated in France.
For a washout valve why are two gate valves required in normal practice?
how to determine H- zone in a column? where it will occur?
Explain what is Hybrid Foundation?
i am laying a base of dimensions 6.5feet by 7feet by 1.25 feet depth how many bags of 25kg cement and how many bags of 25kg sand will i need