how much quantity of cement and sand required for
construction of 10 cum brick work( Brick size
3"*4"*9"(Standard size ) an d for 10 cum construction of SSM
(Size stone masonary) with Cm 1:6 for both.
Answer Posted / arvind vyas
The size of brick be 230mm x 115mm x 75mm
Vol.of brick( w/o mortar) = 0.00198 cum.
Thk.of mortar be 12mm.
vol.of brick with mortar = 242mm x 127mm x 87mm = 0.00267
cum.
No.of bricks in 1 cum. with mortar = 1/0.00267 = 373.99
Say = 374 bricks.
Cement Mortar required = 1-(374 x 0.00198) cum= 0.259 cum.
Say 0.26 cum
Add 15% for frog filling and wastage while execution.
Vol. of wet mortar = 0.299 cum.
Vol. of dry mortar (increase by 30%) = 0.388 cum.
For CM of 1:6
Qty. of cement = 1/7 x (1440 x 0.388) = 0.055 cum.
Qty. of sand = 0.055 x 6 = 0.330 cum
| Is This Answer Correct ? | 8 Yes | 4 No |
Post New Answer View All Answers
How will you Engage Labours on Site?
if 20mm aggregate is coming by weight 25 ton in a 10 wheeler hywa ,then what will be total volume of aggregate in cubic feet.
For what building Built-on balconies are preferable? What are the advantages?
load combinations how many types for staad design purpose?
For the symmetrical continuous beam shown in figure, Prestressed with a force P = 1500 KN along parabolic curve as shown, compute the extreme fiber stresses over the central support for the uniformly distributed load of 24 kn/m. Use load balancing method.
How to calculate the weight of sand am 20mm course aggregate in 1 c.m M25 concrete Which use 400 kg of cement ?
What will be weight of 0.5mm GI sheet per sq.ft?
according to the painting co efficient, we should take the one side of doors (or) windows or both sides?
What is the Null Point of chimney in Power Plant
what is anchorage length,lap length and (dont remember the last one)
VAT and CST ? Which benefits for buyer ? Why benefits?
what is right & short method of measurement of slab&beam
For The preparation of goverment examination Which book i will prefer and by which way i will do the preparation for exam.
What is the diff between cad & cadd?
How many square meter can mason layout chb per hour