how much quantity of cement and sand required for
construction of 10 cum brick work( Brick size
3"*4"*9"(Standard size ) an d for 10 cum construction of SSM
(Size stone masonary) with Cm 1:6 for both.
Answer Posted / sjtbehera
you are given 3”x4”x9” standard size of bricks
After placing mortar it became- 4”x5”x10” =
10.16cmx12.7cmx25.4cm
No of bricks are required=
10/.106x.127x.254=3069 nos
The size of brick without mortar= 3”x4”x9”=
7.62cmx10.1cmx22.8cm
Then net mortar required =10-(3069*.076*.101*.228)
= 4.62cum
Due to frog filling, brick bonding course and
wastage add 15%
Volume of wet mortar= 4.62+4.62x15%=5.30cum
When dry increase this qty. by 1/3rd=
5.30+5.30x1/3=7.06cum
Ratio is =1+6=7 cement = 7.06/7= 1.06 = 29 bags
Sand= 7.06*6= 42.36cum
| Is This Answer Correct ? | 47 Yes | 54 No |
Post New Answer View All Answers
how to read the drawings to find the quantity of steel in a storm water manhole or any other structure?
What are the methods in tiles flooring ? What are the methods in brick work? What are the methods in plastering ? What are the methods in wall tiling?
What ingredients with% found in ppc cement??
Providing ,Cutting, bending and positioning of TMT Bar with cost of binding wire
What is the sugested procedure of water purification for public supply?
can you mail me detailed procedure,entire syllabus and practice papers of mpsc civil engineering branch.I am in third year now
What is the difference between EPC,DBOOT and BOOT.
weight of 1 cft 10mm, 20mm, 40mm aggregate weight of 1cft course sand
Moisture content calculation for diff mix ratio's ??
if dia of slab beam bar is38mm what its clear cover any method of provide clear cover
how to calculate the dry wt of sand and cement for a required design mix?for ex:M20
how i can tak Quantity of mortar in block work
can you give me the details of rate analysis of steel and concrete?
How to calculate ventonite bag in pile ( pile depth 25 m dia 1m)
what r the precaution for high in atp tempareture,low in atp tempareture