how much quantity of cement and sand required for
construction of 10 cum brick work( Brick size
3"*4"*9"(Standard size ) an d for 10 cum construction of SSM
(Size stone masonary) with Cm 1:6 for both.
Answer Posted / b.s.dev
Let the size of brick be 230mm x 115mm x 75mm
Vol. of brick( w/o mortar) = 0.00198 cum.
Thk. of mortar be 12mm.
vol. of brick with mortar = 242mm x 127mm x 87mm
= 0.00267 cum.
No. of bricks in 1 cum. with mortar = 1/0.00267
= 373.99
Say = 374 bricks.
Cement Mortar required = 1-( 374 x 0.00198)cum.
= 0.259 cum.
Say 0.26 cum
Add 15% for frog filling and wastage while execution.
Vol. of wet mortar = 0.299 cum.
Vol. of dry mortar( increase by 30% ) = 0.388 cum.
For CM of 1:6
Qty. of cement = 1/7 x (1440 x 0.388)
= 0.055 cum.
Qty. of sand = 0.055 x 6
= 0.330 cum.
| Is This Answer Correct ? | 188 Yes | 60 No |
Post New Answer View All Answers
how much deduction will be in 32 mm dia HYSD steel bar for 45 and 90 degree bend
how to calculate freeboard in under ground water tank and technical details
what is the difference b/w full length and cutting length?
what is labour consume factor in residential projects
Define What does civil status mean?
what is the most suitable foundation when construct a bird watching tower in a marshy land
What is meant by dimensioning?
the volume of cement req for 70cum of brickwork in 1:6 cement mortar is approx is equal to 3cum 5cum 7cum 1ocum
Explain what is Critical Path Method (C.P.M)?
How do you calculate the power of centrifugal pump?
In block work seawalls what is the purpose of slip joints?
what is the maximum number of course that can be laid according to IS code and the max height.
resins are not soluble in water soluble in spirit used in varnish left behind on evoporation of oil
What out turn civil works
List out the potential risk factors for workers on the construction site?