how much quantity of cement and sand required for
construction of 10 cum brick work( Brick size
3"*4"*9"(Standard size ) an d for 10 cum construction of SSM
(Size stone masonary) with Cm 1:6 for both.
Answer Posted / sudhir
see CPWD ANALYSIS
480 BRICKS PER CUM I/C WASTAGE
1.24 BAGS CEMENT/CUM I/C WASTAGE
1.24*.035*6 = WILL BE THE QTY OF C.SAND REQD/ PER CUM
| Is This Answer Correct ? | 28 Yes | 15 No |
Post New Answer View All Answers
How to calculate paint drums per meter square
detailed calculation of the amount of cement used?
Define polar co ordinates.
how to calclate the SHUTTERING TAKEN CONCRETE LOAD? WHAT IS THE LOAD BEARING CAPACITY IN STEEL SHUTTERING PLATE? WHAT IS THE CONCRETE LOAD IN (MASS) IN THE SHUTTERING PLATE. PLATE SIZE IS 120CM* 90CM CONCRETE WALL LENGTH IS 10M ,WIDE IS 60CM, HEIGHT IS 1.2M PLS TO SENT THE CALCULATION.
the water is flowing through a velocity of 1.5m/s in a pipe of length 2500m and dia 500mm. at the end of pipe a valve is provided. find rise in pressure 1. if the valve is closed in 5 seconds. 2. if the valve is closed instantaneously. take value of c = 1460m/s, pipe to be rigid and bulk modulus of water - 19.692x10' n/sqcm
punj loyed and sapurjl palanjl
Specific gravity of cement?
Providing and casting in situ cement concrete M-25 of trap/granite/quartzite/gneiss metal for rcc, Providing formwork,Curing the concrete and Complete. what is rate per Cum. and what is rate for M-30 Grade Concrete.
how gradation of aggregates effect on slump of fresh concrete?
What is missing report and how to prepare
What is the ratio of grades m5, m7.5, m10, m15, m20, m25, m30, m35, m40?
For removal of formwork of simply supported slab / beam from where to start the deshuttering? ( Max Bending moment of the simply supported beam is in the center hence is it required to start from the supports?)
how to read the drawings to find the quantity of steel in a storm water manhole or any other structure?
how to reduce size of column 450 x 750 to 230 x.... if it is cut in area of bathroom? means it appears in bathroon any shifting or any other option....building is g + 10 and the bathroom is at first floor...
difference between fc and fc'?