Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


What are the deshuttering time for
Salb
Beam
Column
RCC Wall
Footing
Staircase

Answers were Sorted based on User's Feedback



What are the deshuttering time for Salb Beam Column RCC Wall Footing Staircase ..

Answer / tanmay

For columns, walls, vertical form works : 16-24 hrs
Soffit formwork to slabs : 3 days (props to be refixed after removal)
Soffit to beams props : 7 days props to refix after removal.
Spanning up to 4.50m : 7 days
Spanning over 4.50m : 14 days
Staircase : 5 days
Footing : 16-24 hours

Is This Answer Correct ?    126 Yes 8 No

What are the deshuttering time for Salb Beam Column RCC Wall Footing Staircase ..

Answer / hany

Beam sides- 24 hrs.
Beam(spanning upto 3mtrs) bottom- 10 days
Beam(spanning more than 3mtrs) bottom- 21 days
slab (spanning upto 3mtrs)- 7 days
Slab (spanning more than 3mtr)- 14 days
rcc wall- 24 hrs
Footing- 24 hrs
Staircase soffit- 7 days

Is This Answer Correct ?    40 Yes 10 No

What are the deshuttering time for Salb Beam Column RCC Wall Footing Staircase ..

Answer / b m sarwe

Beams 21 days
beams side 1 day after casting
slab 7-14 days
columns 1 day after casting
wall 1 day after casting
footing casting next day
Deshuttering works

Is This Answer Correct ?    8 Yes 2 No

What are the deshuttering time for Salb Beam Column RCC Wall Footing Staircase ..

Answer / swadesh

aprox 7 Days for Slab (If RCC used from Batching Plant)

Is This Answer Correct ?    13 Yes 10 No

What are the deshuttering time for Salb Beam Column RCC Wall Footing Staircase ..

Answer / farhat abbas naqvi

For deshuttering any concrete structure after pour to take in note the climate and design mix. For columns and beams sizes plays the major role. Usage of flyash also plays role in settling time.

Is This Answer Correct ?    4 Yes 2 No

What are the deshuttering time for Salb Beam Column RCC Wall Footing Staircase ..

Answer / h r mishra

Slab 7 days
Beam 10 days
wall, footings 24 hours

Is This Answer Correct ?    5 Yes 5 No

What are the deshuttering time for Salb Beam Column RCC Wall Footing Staircase ..

Answer / kirishnasekar m

all sides - next day itself (24 hours)

slab < 4.5 m-7 days

slab > 4.5 m-14 days

beam & arches < 6.0 m-14 days

beam & arches > 6.0 m-21 days

staircase waist-7days, after removal of shutter, props to be fixed for 3 days

Is This Answer Correct ?    0 Yes 0 No

What are the deshuttering time for Salb Beam Column RCC Wall Footing Staircase ..

Answer / simon nagaiya

Formwork Removal Time
-------------------------------
Sides of Walls, Columns and Vertical faces of beam - 24 hours to 48 hours (as per engineer’s decision)

Slabs (props left under) - 3 days

Beam soffits (props left under) - 7 days

*Removal of Props of Slabs:*

i)Slabs spanning up to 4.5m - 14 days

ii)Slabs spanning over 4.5m - 14 days

*Removal of props for beams and arches*

i)Span up to 6m - 14 days

ii)Span over 6m - 21 days

Is This Answer Correct ?    3 Yes 4 No

What are the deshuttering time for Salb Beam Column RCC Wall Footing Staircase ..

Answer / krishan

slab-7days
columan-24hours
beam bottom-3days
beam side-24hours
rcc wall-48hours
footing-12hours
staircase-7days

Is This Answer Correct ?    6 Yes 9 No

What are the deshuttering time for Salb Beam Column RCC Wall Footing Staircase ..

Answer / md.khorshed alam

slab-14days
columan-24hours
beam bottom-7days
beam side-24hours
rcc wall-48hours
footing-12hours
staircase-7days

Is This Answer Correct ?    1 Yes 4 No

Post New Answer

More Civil Engineering Interview Questions

How to measure the requirement of cement n sand for 12mm and 20mm plastering thanks in advance

0 Answers  


I want to know the material required per square foot in rcc roof. i.e. steel: kg/foot, cement/foot etc.

0 Answers   TVO,


why the cube depth is 150 mm which is used for testing

1 Answers   L&T,


how to distinguish TMT n Tor steel?

2 Answers  


What is the cost of shuttering per Sqm.? How it is calculate by thumb rule...?

0 Answers  


How to identify the vitrified tile and ceramic tile by observation only after executing the job.

0 Answers  


where is shear stress max and min in rcc beams?

3 Answers   NSL,


where do Tie beams used in foundations?

1 Answers   Architects,


undisturb samples are obtained by direct excavation thin walled sampler thick walled sampler none of this

1 Answers  


WHAT IS YOUR CURRENT SALARY

0 Answers   VGN Developers,


what does 1 in 30 or 1 in 40 mean when constructing camber in roads.

5 Answers   Simplex,


a)If column dimensions are 250*400mm , what will be cutting length for 8mm stirrups and how to calculate it? b) If beam dimensions are 200*400mm , beam coveris 25mm , slab cover is 20mm , what will be the cutting length for stirrups? c)Column dimensions are 250*400mm , reinf. is 12nos. bar of 16mm dia , stirrups provided are two legged, what will be the length of each ring? Regards

27 Answers   Alfaraa, Speco, Supertech, Welspun,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)