What are the deshuttering time for
Salb
Beam
Column
RCC Wall
Footing
Staircase
Answers were Sorted based on User's Feedback
Answer / tanmay
For columns, walls, vertical form works : 16-24 hrs
Soffit formwork to slabs : 3 days (props to be refixed after removal)
Soffit to beams props : 7 days props to refix after removal.
Spanning up to 4.50m : 7 days
Spanning over 4.50m : 14 days
Staircase : 5 days
Footing : 16-24 hours
| Is This Answer Correct ? | 126 Yes | 8 No |
Answer / hany
Beam sides- 24 hrs.
Beam(spanning upto 3mtrs) bottom- 10 days
Beam(spanning more than 3mtrs) bottom- 21 days
slab (spanning upto 3mtrs)- 7 days
Slab (spanning more than 3mtr)- 14 days
rcc wall- 24 hrs
Footing- 24 hrs
Staircase soffit- 7 days
| Is This Answer Correct ? | 40 Yes | 10 No |
Answer / b m sarwe
Beams 21 days
beams side 1 day after casting
slab 7-14 days
columns 1 day after casting
wall 1 day after casting
footing casting next day
Deshuttering works
| Is This Answer Correct ? | 8 Yes | 2 No |
Answer / swadesh
aprox 7 Days for Slab (If RCC used from Batching Plant)
| Is This Answer Correct ? | 13 Yes | 10 No |
Answer / farhat abbas naqvi
For deshuttering any concrete structure after pour to take in note the climate and design mix. For columns and beams sizes plays the major role. Usage of flyash also plays role in settling time.
| Is This Answer Correct ? | 4 Yes | 2 No |
Answer / h r mishra
Slab 7 days
Beam 10 days
wall, footings 24 hours
| Is This Answer Correct ? | 5 Yes | 5 No |
Answer / kirishnasekar m
all sides - next day itself (24 hours)
slab < 4.5 m-7 days
slab > 4.5 m-14 days
beam & arches < 6.0 m-14 days
beam & arches > 6.0 m-21 days
staircase waist-7days, after removal of shutter, props to be fixed for 3 days
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / simon nagaiya
Formwork Removal Time
-------------------------------
Sides of Walls, Columns and Vertical faces of beam - 24 hours to 48 hours (as per engineer’s decision)
Slabs (props left under) - 3 days
Beam soffits (props left under) - 7 days
*Removal of Props of Slabs:*
i)Slabs spanning up to 4.5m - 14 days
ii)Slabs spanning over 4.5m - 14 days
*Removal of props for beams and arches*
i)Span up to 6m - 14 days
ii)Span over 6m - 21 days
| Is This Answer Correct ? | 3 Yes | 4 No |
Answer / krishan
slab-7days
columan-24hours
beam bottom-3days
beam side-24hours
rcc wall-48hours
footing-12hours
staircase-7days
| Is This Answer Correct ? | 6 Yes | 9 No |
Answer / md.khorshed alam
slab-14days
columan-24hours
beam bottom-7days
beam side-24hours
rcc wall-48hours
footing-12hours
staircase-7days
| Is This Answer Correct ? | 1 Yes | 4 No |
which percentage is maximum in good quality cement?
How will be cutting in timber plate size 600*400 column size
12mm diameter iron bar having 1m length how much kg weighted ?
what is cement mortar cube size and strength in 3days, 7days and 28days
How to construct a water sump in a rocky soil?
Can anybody help me by attaching files , formats for quality checks of common building materials like cement , concrete , bricks , sand and aggregates? Regards,
45 Answers CDS, L&T,
how to calculate detail quantity of bricks and mortar for 500 cu.ft masonry work. consider wall thickness 9 inches
how to calculate shuttering measurement of beam and slab
how to calculate steel in slabs ?
# 1. Size of slit content in sand. # 2. Gravity of sand # 3. Water observation capacity of sand. # 4. minimum crushing Strength of sand.
How to calculate cement quantity in m20 concrete
2 Answers nnovative Constructions, Shapoorji Pallonji Group(SPCL),
What is Lap Length??????
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)