What are the deshuttering time for
Salb
Beam
Column
RCC Wall
Footing
Staircase
Answers were Sorted based on User's Feedback
Answer / tanmay
For columns, walls, vertical form works : 16-24 hrs
Soffit formwork to slabs : 3 days (props to be refixed after removal)
Soffit to beams props : 7 days props to refix after removal.
Spanning up to 4.50m : 7 days
Spanning over 4.50m : 14 days
Staircase : 5 days
Footing : 16-24 hours
Is This Answer Correct ? | 126 Yes | 8 No |
Answer / hany
Beam sides- 24 hrs.
Beam(spanning upto 3mtrs) bottom- 10 days
Beam(spanning more than 3mtrs) bottom- 21 days
slab (spanning upto 3mtrs)- 7 days
Slab (spanning more than 3mtr)- 14 days
rcc wall- 24 hrs
Footing- 24 hrs
Staircase soffit- 7 days
Is This Answer Correct ? | 40 Yes | 10 No |
Answer / b m sarwe
Beams 21 days
beams side 1 day after casting
slab 7-14 days
columns 1 day after casting
wall 1 day after casting
footing casting next day
Deshuttering works
Is This Answer Correct ? | 8 Yes | 2 No |
Answer / swadesh
aprox 7 Days for Slab (If RCC used from Batching Plant)
Is This Answer Correct ? | 13 Yes | 10 No |
Answer / farhat abbas naqvi
For deshuttering any concrete structure after pour to take in note the climate and design mix. For columns and beams sizes plays the major role. Usage of flyash also plays role in settling time.
Is This Answer Correct ? | 4 Yes | 2 No |
Answer / h r mishra
Slab 7 days
Beam 10 days
wall, footings 24 hours
Is This Answer Correct ? | 5 Yes | 5 No |
Answer / kirishnasekar m
all sides - next day itself (24 hours)
slab < 4.5 m-7 days
slab > 4.5 m-14 days
beam & arches < 6.0 m-14 days
beam & arches > 6.0 m-21 days
staircase waist-7days, after removal of shutter, props to be fixed for 3 days
Is This Answer Correct ? | 0 Yes | 0 No |
Answer / simon nagaiya
Formwork Removal Time
-------------------------------
Sides of Walls, Columns and Vertical faces of beam - 24 hours to 48 hours (as per engineer’s decision)
Slabs (props left under) - 3 days
Beam soffits (props left under) - 7 days
*Removal of Props of Slabs:*
i)Slabs spanning up to 4.5m - 14 days
ii)Slabs spanning over 4.5m - 14 days
*Removal of props for beams and arches*
i)Span up to 6m - 14 days
ii)Span over 6m - 21 days
Is This Answer Correct ? | 3 Yes | 4 No |
Answer / krishan
slab-7days
columan-24hours
beam bottom-3days
beam side-24hours
rcc wall-48hours
footing-12hours
staircase-7days
Is This Answer Correct ? | 6 Yes | 9 No |
Answer / md.khorshed alam
slab-14days
columan-24hours
beam bottom-7days
beam side-24hours
rcc wall-48hours
footing-12hours
staircase-7days
Is This Answer Correct ? | 1 Yes | 4 No |
Difference between overlap and development length of rod. Thanks.
how will calculate the lift load in high rise buildings
function of stirrup in rcc beam & column?
2 Answers KMDA-Kolkata Metropolitan Development Authority, TK Group,
How can i design the beam . Explain with one example
standard sand use?
can we make bricks using m10 grade cement concrete and what would be the ratio of raw materials used and price per brick ?
What Is the Thumb rule to calculate depth and dia of pile required to carry specified load on differeent soil
How much steel required for 1 sq. meter area?
1 Answers Aditya Constructions,
Allowable wastage for ready mix concrete?
What are the strongest shapes in building?
What is the calculation for finding cement and sand for 10' * 12' area ratio 1:6 thickness 12 mm
Which types of Water Proofing to Be used in Swimming Pool.
2 Answers CCEL, Ideal Construction,