How to calculate cement quantity in m20 concrete
Answers were Sorted based on User's Feedback
M20 concrete means 1:1.5:3
M20 = 1:1.5:3
Volume = 1+1.5+3=5.5
Total volume ingredients for using =1.57
Volume of broken stone Require = (3/5.5) x 1.57 = 0.856 m3
Volume of sand Require = (1.5/5.5) x 1.57 = 0.471 m3
Volume of cement = (1/5.5) x 1.57 = 0.285 m3
= 0.285 x1440 = 411 kg = 8.22 bags
Is This Answer Correct ? | 14 Yes | 1 No |
calculation of cement quantity in m20 concrete
M20 = 1:1.5:3
Volume = 1+1.5+3=5.5
Total volume ingredients for using =1.57
Volume of broken stone Require = (3/5.5) x 1.57 = 0.856 m3
Volume of sand Require = (1.5/5.5) x 1.57 = 0.471 m3
Volume of cement = (1/5.5) x 1.57 = 0.285 m3
= 0.285 x1440 = 411 kg = 8.22 kgs
Is This Answer Correct ? | 4 Yes | 2 No |
What is the use of extruded feature in solidsworks?
why do we provide haunch for drains and culverts?
what is the anchorage length of reinforcement.
volume of one cement bag
4 Answers Grand Peaks, Omace, Swasudha Infra,
this is jagdesh from vizag, IM GOING 2 ATTEND BHEL interview on 14th dec. im a civil engg. graduate. plzz let me know the pattern & few questions of the interview if possible. plz reply at jd_marc@yahoo.com
How much quantity of cement,sand,stone used to build 1 cum of cc road??
0 Answers Pandey Construction Company,
How to test the soil compaction test?
Name the main components of a cad gui?
if a pipe those configuration (ASTM c 76 class b 450mm dia 2500mm length) fixing for water course those lining of water is 7000 running meter. my question is that if 8 joints of pipe ls leakage and we have not permission to stop the water so which treatment we apply on joint in that in condition.
procedure for preliminary selection of size of column of 5 storey building
How can we calculate the cement Quantity in M25?
2 Answers JK Associates, Vardhman, Wave Infratech,
how much quantity of tile placing can be finished by one mason per day?