What are the deshuttering time for
Salb
Beam
Column
RCC Wall
Footing
Staircase
Answer Posted / krishan
slab-7days
columan-24hours
beam bottom-3days
beam side-24hours
rcc wall-48hours
footing-12hours
staircase-7days
| Is This Answer Correct ? | 6 Yes | 9 No |
Post New Answer View All Answers
Mention different types of roof systems?
what is work of planning deptt. in any construction compny (in road project)
plz drive the formula d2/162.162 for the calculation of weight of steel bars????
explain the advantages of total stasion
relation bet Coefficient consolidation Cv, time factor Tv, drainage path d, & time t is Cv=d2Tv/t Cv=d2t/Tv Cv=tTv/d2 Cv=Tv/td2
PLS.......... ANY ONE CAN FORWARD ME PREVIOUS QUESTION PAPER hpcl civil engg
how can we calculate steel value, depending on load
What is meant by Crystal Concrete?
How much cement,sand,bricks and water needed for 1square metre brick work?
sir please send me campus placement questions in civil engineering
can you mail me detailed procedure,entire syllabus and practice papers of mpsc civil engineering branch.I am in third year now
Define What is the force exerted by the Tacoma narrows bridge?
what is the tensile strength of 10swg and 8swg gabion wire?
What you understand by building codes?
GIVE US YOUR FULL DETAIL OF THE FOLLOWING… FULL NAME.. PERMENENT MAILING ADDRESS DIRECT CONTACT NO E MAIL ADDRES.