What are the deshuttering time for
Salb
Beam
Column
RCC Wall
Footing
Staircase
Answer Posted / hany
Beam sides- 24 hrs.
Beam(spanning upto 3mtrs) bottom- 10 days
Beam(spanning more than 3mtrs) bottom- 21 days
slab (spanning upto 3mtrs)- 7 days
Slab (spanning more than 3mtr)- 14 days
rcc wall- 24 hrs
Footing- 24 hrs
Staircase soffit- 7 days
| Is This Answer Correct ? | 40 Yes | 10 No |
Post New Answer View All Answers
What are the causes of building collapse?
What is the nature of duties & responsibilites senior civil engineer ?what is self confident & satisfaction should be a senior civil engineer?
what is the hanekom repairing material after concreting work
If a slab concrete is placed with M-20 grade concrete, actually it has to be placed with M-30. what are the rectifications / measures to be taken after concreting is done.
How do we test on design and style in a software?
Can rice husk ash be used instead of coal fly ash for manufacture of clc/ foam concrete
cement mortor 1:5 for 30 m2 12 mm tk plastering so how to calcualte its rate
Define current ucs?
Before casting a basement roof slab which is connected with retaining wall surcharge load (i.e. sand or earth filling) outside the retaining wall is prohibited because of––
How do we determine the specific gravity of a cement?
if in column reinforcement lower dia connect to higher dia then from wher we want to start higher dia steel
Why the statue of liberty is made of copper?
cement, sand, aggregate,reinforcement & concrete consumption per square feet in multi storeyed building
kindly mail me by attaching files , formats for quality checks of common building materials like cement , concrete , bricks , sand and aggregates plz send my email id- VMANDAL91@gmail.com
please send me bhel questions on rupesh.017@rediffmail.com