What are the deshuttering time for
Salb
Beam
Column
RCC Wall
Footing
Staircase
Answer Posted / simon nagaiya
Formwork Removal Time
-------------------------------
Sides of Walls, Columns and Vertical faces of beam - 24 hours to 48 hours (as per engineer’s decision)
Slabs (props left under) - 3 days
Beam soffits (props left under) - 7 days
*Removal of Props of Slabs:*
i)Slabs spanning up to 4.5m - 14 days
ii)Slabs spanning over 4.5m - 14 days
*Removal of props for beams and arches*
i)Span up to 6m - 14 days
ii)Span over 6m - 21 days
| Is This Answer Correct ? | 3 Yes | 4 No |
Post New Answer View All Answers
to draw bm diagrams for portal frames under different loadings//
what are the challenges of being a team leader and a supervisor?
how i convert mm into standard wire guage (SWG)no.
Why are steel plates inserted inside bearings in elastomeric bearing?
importance of the soundness test to determine the quality of cement use for any construction
how to calculate MR 9(derivation)
How to calculate the quantity of ingredients of M20 grade concrete?
In tower foundation, on the time of 3 mtr pit RCC casting if water and mud is their surface of PCC then what will be do?
what is smart building materials?
1. What is coefficient use for calculation of shuttering. 2. What is coefficient use for calculation of reinforcement in one cum of concrete.
how much quantity of 1.5" nails and 2.5" nails are required for conventional formwork shuttering?
What year was the keystone power plant in Indiana County constructed?
what is difference between fluidity and workability also how palsticizer works
how to remove the quantity of metal 1 and metal 2 in concrete
how much concrete solid/hollow block are manufacture per 50 kg cement bag in differnent sizes like 400x200x200mm, 400x200x150mm, 400x200x100mm. And need proper ratio as per sale quantity. pls send my mail mathi7599@gmail.com searching last two years not yet get pls find and enclosed pls. need practical analysis.