What are the deshuttering time for
Salb
Beam
Column
RCC Wall
Footing
Staircase
Answer Posted / tanmay
For columns, walls, vertical form works : 16-24 hrs
Soffit formwork to slabs : 3 days (props to be refixed after removal)
Soffit to beams props : 7 days props to refix after removal.
Spanning up to 4.50m : 7 days
Spanning over 4.50m : 14 days
Staircase : 5 days
Footing : 16-24 hours
| Is This Answer Correct ? | 126 Yes | 8 No |
Post New Answer View All Answers
What are the advantages of cad?
sir tell me the formula for calculating the volume of 380mm dia double under reamed pile of 4.0 mts depth.
What tor stands for in tor steel?
1.How much batten required for 1 sqm Shuttering. 2.how much pipe & clamps required for staging of 100 sqm shuttering at 5.0 m height.
why we use aggregate,sand with cement in concrete?
is there any thumb rule for calculating construction cost of the building with pile foundation per sft. area?
how much need sand and cement for 1 cft roof construction?
could u tell me how to used deform stell bar in reinforce concret?i wanna know the general using in the site!
What are segregation and bleeding?
what is mc arther pile?
What is the difference between tor steel and tmt steel?
how many kg cement & fine sand reqird in one sq meter 1:6 mortar ratio?
how many numbers of 4inch bricks and get consumed in 9 inch BB masonary wall in cubic feet.plz send my below e.mail adress
What is the primary difference between adsorption and absorption?
how many type of admixtures for water stored structure?