how much cement is required for 100 sft plastering of ratio
1:4
Answers were Sorted based on User's Feedback
Answer / ahmed j (if u any question to
Thikness Of Plaster 18 To 20mm
Sand in 1Cubic mtr =1.25 For All Ratio
Cement in 1 Cubic mtr For
1.3 = .21
1.4 = .31
1. Thikness Of Plaster For 1st Coat is Roush Coat 12mm
*Propotion of C:M For 1st Coat With Ratio 1:6 , 1:5,
2. Thikness Of Plaster For 2nd Coat is Fine Coat 6 to 8mm
*Propotion Of C:M For 2nd Coat With Ratio 1:4 , 1:3
Area Is 100sft / 3.28^2 =
9.295 * 0.008=
Area * Thikness
0743*.31=
Volume * Ratio
0.023*1440=
Quantity * Cement Volume
Cement Quantity Required Is 33.20 Kgs (With Out Wastage)
| Is This Answer Correct ? | 35 Yes | 15 No |
Answer / qudrat
what is the cost of cement for plaster 2'' for the ratio of 1 to 4
| Is This Answer Correct ? | 7 Yes | 3 No |
Answer / shailesh srivastava
6mm thk far 1 sqm
Qty executed=1x1x.006
20% extra for voids & wastage=.0012
total =.0072
30% extra for dry =.00216
Total required qty =.00936 cum
Cement =.00936/5
=.001872 cum
far 1 sqft =.001872/10.76
far 100 sqft =100*.001872/10.76cum
=100*1440*.001872/10.76
=25.052 kg
| Is This Answer Correct ? | 9 Yes | 19 No |
Answer / ndd
In this question plastering thikness is not mentioned.
Consider,plastering ( Cement and sand)thickness = 10mm
100 Sqft = 9.29 Sqm
-------------------------------------------------------
Wet Mortar volume= 9.29 X 0.01Cum =0.0929 Cum
Dry Mortar volume = 0.0929 X 1.15 =0.106835 Cum
Cement = 1/4 X 0.106835 X 1400 Kg =37.392 Kgs
(Volume of cement is ignored )
Hence for 100 Sqft area,and 10mm thick plastering the
cement quantity required = 37.40 Kgs ( Without wastage)
| Is This Answer Correct ? | 7 Yes | 20 No |
Answer / karthikeyan.n
1 sq.m = 10.76 sq.ft.
100 sq.ft = 9.29 sq.m
cement required for 10 sq.m = 3/(1+4)=.6*1440/50 = 17.28bag,
100sq.ft cement required = 1.728*9.29 = 16.05 bags
| Is This Answer Correct ? | 34 Yes | 93 No |
what is the multiplying factor for diffrent types of pcc/rcc ratios?
How to calculate the Quantity of Steel for Footing?
WHAT IS THE LAP LENGTH FOR COLUMN WITH DESIGN MIX M-35 RCC
7 Answers Omaxe, Shoba Devlopers,
for 100sft of Cement plastering ratio 1:6 How much quantity of cement and sand required.
6 Answers J.K. Organization, L&T,
Is it possible 18" beam rest on 18" beam and created the junction on beam instead of column?
why steel tanks are provided (a) for water pressure (b) for wind pressure (c) for earthquake pressure
What is the basic difference between OPC
what is the bend correction for 90 degree of bend in any dia of HYSD steel reinforcement as per IS code ?
What is the difference between "working stress method" And "limit state method"?
what is the minimum compressive strength of clay brick
0 Answers Ananya Construction Infrastructure, VNC,
How much steel required in 900 square feet slab?
17 Answers RCC, Sai Steel Corporation, TATA,
How much steel and concrit required in 1000 square feet slab?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)