Given a selection of 28 day cube test results for concrete placed of design mix C 35 and not all of which are greater then 35 MPa, how does one decide if the concrete in place is satisfactory. Are there a minimum number of cubes that need to be tested to decide that?
Answers were Sorted based on User's Feedback
Answer / himanshu
95% of the total no. Of cubes tested mus paas the design limit , in your case its 35 , However 5% can b neglected if more than 5% fail for 35Mpa the the mix i not proper. There is no definite no. Of cubes to b tested.
Is This Answer Correct ? | 1 Yes | 0 No |
Answer / raju goyal
As per my view : At the time of casting of any structure we would have to taken six samples from the each load or batch in which 3 samples keep 7days and 3 samples for 28 days testing. The 7days samples should have minimum 75 % strength and 95 % strength in 28 days should be gained of it's characteristics strength .
Is This Answer Correct ? | 0 Yes | 0 No |
What is the meaning of soil reinforcement?
How to do base isolation using ETABS software?
what is the procedure of plastering..?
Why nautical mile is different from statute mile?
What is meant by Rolling Margin? & which material will effect in this ?
what is mail role & relationship between senior Civil engineer to consultants , Construction manager ,project manager, project engineer ,Technical engineer & qa/qc engineer ? what is the responsibilites of Senior Civil Engineer?
what is the mix design for M:60 with micro silica andmetakaoline?
How find out Rolling margin of steel dia.wise?
how to caluclate sienerge qty in construction in ap
0 Answers Rites, VR Residency,
what is the difference between compaction and consolidation??
mix design procedure, i.e m15 to m40
IN LOW RISE BUILDING PER SQ FT HOW MANY MATERIAL REQ. SAND &CONCREATE&CEMEBT