what would be the rqmnt. of cement and sand (1:6)for
building brick wall and also 20mm thick plaster on the wall
by same ratio?
Answer / p.rambabu
1.approximately we can calculate the requirement of brick
work for 1cum of 1:6 ratio
ans:cement=(1/6)*1440=239.999*0.21=50.399/50=1.007bags/cum.(here
the ratio of 0.21is the approximately dry volume of sand).
2.for 20mm thk plastering calculation,
a.first we can calculate the volume of plastering area,
b.increase it's volume to 20% because of the honeycomb
work& miscellaneous works.
c.multiply this value with dry volume of 1.3.
for 1:6 for 20mm thk of 100sq.m
cement=(1/7)*1.3*2.2=0.408*1440=587.52/50=11.750bags.
Is This Answer Correct ? | 2 Yes | 3 No |
hi every body..i have applied for RRB section engineers CIVIL.i wanna prepare for that,so can any one suggest me some books and where can i get the syllabus for this..i would be vry greatful if any one can help in this regard
HOW TO CLACULATE CEMENT AND SAND CONSUMPTION FOR THE STAIRCASE KOTA FLOORING IN THE RATIO OF 1:4 50 MM THICKNESS
which one is economical construction brick masonry or sold block masonry?
what is mean by k150
How to calculate the amount of cement & sand required for plastering work with ratio 1:4 please give me an answer with detailed step.
6 Answers DSR Management, Simplex,
the volume of 50kg bag is 27 lit 24.7 lit 44.7 lit 42.9 lit
what is the standard brick frog size ?
What are the different softwares used for cad?
1) a)to prepare mortar for bricklaying how much amount of water should be added for its maximum strength and workability(to avoid cracks which results, when high quantity of water is added)?is their a formula or ratio? b) suppose we want to make 1:3 mortar,what is the best way to measure cement ,sand and water and how? c)time before which freshly prepared mortar should be used? d)proper way to mix and make mortar? e)when should curing start after laying bricks and for how long?and also how many hours per day? f)what is shear wall (please in terms of layman lol) bookish definisions are confusing.... g) and last,acc to codes what are max no. of course that should be laid in a day.
Normally in slabs, steel quantity is not added when you calculating concrete quantity for that slab, why it is not added ?
What is the number of IS code of practice to be followed for hydraulic design of sewerage pipe line?
in design case of structural member best suitrable percentage of steel limit is what