how much cement is required for 100 sft plastering of ratio
1:4
Answer Posted / shailesh srivastava
6mm thk far 1 sqm
Qty executed=1x1x.006
20% extra for voids & wastage=.0012
total =.0072
30% extra for dry =.00216
Total required qty =.00936 cum
Cement =.00936/5
=.001872 cum
far 1 sqft =.001872/10.76
far 100 sqft =100*.001872/10.76cum
=100*1440*.001872/10.76
=25.052 kg
| Is This Answer Correct ? | 9 Yes | 19 No |
Post New Answer View All Answers
Explain what is progress payment?
What is the use of extruded feature in solidsworks?
How do you prepare Material Recovery Statement for deduction from contractors bills?
Explain the water bound macadam roag
Explain why concrete barriers have curved surface profiles?
why do we not deduct volume of steel to find actual volume of concrete in practical???
Kindly post me previous year interview questions with answer for post of Manager (civil engg.) for NTPC, IOC , GAIL etc. I have interview on july 2013.I will be very grateful to you. Please guide me.
pls tell estimate for 1 kilometre length random rubble masonry 0.90 metre height 0.600 metre width
What is the biggest dam in america?
How many litres of water used for curing of 1000sqft of slav
how to calculate cost of raw materials of a building for 1000 sqft & also consolidated cost of labour in a 1000 sqft building
from one meter cube of stone masonry structure how much cubic meter of cement mortar we use as our estimation 25-30% is that correct for estimation of quantity of sand and cement(2:1) proportion of mortar
What are the basic use of runners and standards of pipelines?
What is oneside mat. And explain
how to do cementicious paint for rcc walls of cw pump house