how much cement is required for 100 sft plastering of ratio
1:4
Answer Posted / karthikeyan.n
1 sq.m = 10.76 sq.ft.
100 sq.ft = 9.29 sq.m
cement required for 10 sq.m = 3/(1+4)=.6*1440/50 = 17.28bag,
100sq.ft cement required = 1.728*9.29 = 16.05 bags
| Is This Answer Correct ? | 34 Yes | 93 No |
Post New Answer View All Answers
What materials were used to build the golden gate bridge?
What do you mean by the word 'shear'?
As we know that steel is a tension member but why we are using STRUCTURE STEEL as a COLUMN (Without concrete) where column is a compression member and compression strength of steel is very low
What is the difference between EPC,DBOOT and BOOT.
how much one carpenter can doing shuttering of slab in one day
What is the crank length in the slab?
Which prize is the alternative to the NOVEL Prize?
What is the best type of wood glue?
Floor to floor high of domestic building is 3m design a quarter turn staircase starting assume taken give a suitable diagram of it?
How can you distinguish between sorption, absorption and adsorption?
Pls explain me about tension and compression in a flat slab
how to absorb to site basic corrections? which are the important correction?
which red: used in roof teping, then use only cement
Describe Briefly The Various Methods Of Concrete Curing?
what is the use of beam end forces while using a staad ? wha they are show