how much cement is required for 100 sft plastering of ratio
1:4
Answer Posted / qudrat
what is the cost of cement for plaster 2'' for the ratio of 1 to 4
Is This Answer Correct ? | 7 Yes | 3 No |
Post New Answer View All Answers
How cracks in concrete can be avoided?
How to calculate laplength for 3 floors
how calculate the bearing from two coordinates?
why is M30 grade Concrete use for Foothing & Column M50
What do you mean by honeycomb in concrete?
what is meaning of inverted beam.is it way to provide double mat in slab one at bottom and another at topif we go for provision of inverted beam. shall we construct structure with out plinth beam for us we have to construct small bus shelter
) Design a gussetted base for a column section consisting of one sc 250 with two cover plates 300 x 25 mm carrying an axial load of 2500 KN. The S.B.C. of soil is 250 KN/m2 and the permissible bearing pressure on concrete is 4000 KN.
it is possiblee to produce concrete with out cracks...
How do you determine specific gravity of cement?
Hollow block masonry in cement mortar 1:4, 40×20×20cms in superstructure take 10sqm.I want calculation of brick sand
How do you calculate reinforcement weight of steel?
If density of cement is 1500 Kg/m3, the how is specific gravity 3.15 ? (Density of water is 1000 Kg/m3)
what is the weight of 12mm aggregates?
what is the sequence of the activities in the typical under ground water tank including civil & MEP works.
What is the quantity of metal 1 & metal 2 to be used in 100 cft concrete?