how to calculate 1:2:4 ratio concrete cement, sand, metal
and water please give me brief calculation
Answers were Sorted based on User's Feedback
Answer / shubham kumar
M15=1:2:4. for cement concrete. 101â„… right answer
calculate
a. cement. 1×1.54/7=0.22cum×28.8(for bag)=6.33 bags
b. sand 2×1.54/7=0.44 cubic metre
c. aggregate. 4×1.54/7=0.88 cum
Is This Answer Correct ? | 8 Yes | 5 No |
Answer / shahnawaz
calculation for 1:2:4(M15)
take 50%extra for shrinkage/wastage
1+.5=1.5/1+2+4=.214
now, in 1 bag of cement having qty =.0347cum
so,.214/.0347=6.16 no of bags.
for sand,.214x2=.428 cum
for aggregate,.214x4=.856cum
for cft just x35.31
Is This Answer Correct ? | 7 Yes | 5 No |
Answer / laxmikant kirpankar
DENSE VOLUME OF 1 M3 OF 1:2:4 m15 Conc.=1.52m3 approx.
Ratio (1+2+4)=7
=1.52/7= 0.22m3 Cement required for 1m3 of conc
Proportion(1:2:4)
1 Part of Cement=( 1x0.22=0.22 m3 Cement required for 1m3)
2 part of sand =(2x0.22= 0.44m3 Sand required for 1m3)
4 Part of aggregate=( 4x0.22=0.88m3 Aggregate for 1m3)
Note: Volume of 1 Bag of Cement = 0.035m3
Hence 0.22m3/ 0.035= 6.28 Bags of cement required for 1m3 of concrete
Is This Answer Correct ? | 2 Yes | 0 No |
Answer / venkatesh babu rj
Cement - 1 Part
Sand - 2 part
Aggregate - 4part
Cement = 1440 x 0.9/4
= 324Kg/m3 or 6.48Bags(324/50).
Sand = 1440 x 0.45/2
= 324kg/m3.
Aggregate = (1.25x4x6.48)/35.315
= 0.917Cu.m
Is This Answer Correct ? | 4 Yes | 3 No |
Answer / engr. hammad khan
I'm a professional civil engineer, here is a perfect simple method.
Let suppose you have total 100 cft of concret.
1.How to calculate number of cement bags.
=100*1.54/(7*1.25)
2. Amount of sand in cft
=no.s of bags*1.25*2
3. Amount of crush in cft
= amount of sand*2
Is This Answer Correct ? | 1 Yes | 0 No |
Answer / khurram
ratio is 1:2:4 sum is equle 7
1 bag cement is equle to 1.25
total quantity resum is 200 cft
for cement bags ;200 divide bt ratio which is 7 answer is 28.57
than
28.58 multiply by 1 wich is first figure of ratio
than divided by 1.25 which is volume of 1 cement bag
the answer is calkled cement bags
example
cement bags ;200/7=28.57*1/1.25=22.85 bags
for sand 200/7=28.57*2=57.14 cft
for crash 200/7=28.57*4=114.25 cft
Is This Answer Correct ? | 38 Yes | 38 No |
Answer / satish kumar lade
Constant of Dry volume /m3 = 1.5
1:2:4 = 1+2+4=7
1.5/7=0.214
1 cum = 1440 kg cement
1440 x 0214 = 308.57 kg
Is This Answer Correct ? | 0 Yes | 0 No |
Answer / farhan tanoli
In order to estimate the quantity of loose materials to have
100 cubic feet wet concrete we first multiply the wet
concrete by 1.54.
e.g 100x1.54=154 cubic feet of dry materials we need.
now come to the ratio of concrete which is 1:2:4 so sum of
the ratio will be 1+2+4=7
calculating separately each material:
Cement: 1/7x154 = 22 cubic feet
where 1 bag of cement measured 1.25 cubic feet approx
therefore 22/1.25 = 17.6 bags of cement. 1 bag contains 50kg
cement so total cement by weight we need for 100 cubic feet
concrete = 17.6x50 = 880kgs
sand: 2/7x154 = 44 cubic feet
coarse aggregate: 4/7x154 = 88 cubic feet
Is This Answer Correct ? | 0 Yes | 0 No |
Why we are not provide bar in the centre of the column and bar?
"how can we find the approximate quantity of materials using in a building or total Expenditure in percentage for rough estimate after known the construction area(sqm)".please if you know something about that please post the answer.
What is the difference between vitrified and ceramic tiles?
CROSS SLOPE OF Macadam Construction
what is CBR Test
what is the maximum number of course that can be laid according to IS code and the max height.
How To Measure Honey Comb Full Brick Work, Can we deduct Hole, If Yes, how to Calculate Rate Analysis
how do i find the fixed end moments in the fixed beams with the use of general method?
the minimum percentage of steel for 2m rcc slab
which is higher specific gravity or bulkdensity
how to calculate the quantity of steel used for construction..
show answer/ calculate-1-2-4 ratio-concrete -cement-sand- metal-water - please brief calculation