how to calculate 1:2:4 ratio concrete cement, sand, metal
and water please give me brief calculation
Answer Posted / engr. hammad khan
I'm a professional civil engineer, here is a perfect simple method.
Let suppose you have total 100 cft of concret.
1.How to calculate number of cement bags.
=100*1.54/(7*1.25)
2. Amount of sand in cft
=no.s of bags*1.25*2
3. Amount of crush in cft
= amount of sand*2
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
how to do cementicious paint for rcc walls of cw pump house
how meny typs of renging rod?
How to calculate Acctually Brickwork Quantity in Honey Comb Brick in circular Soak Pit
TELL ME THE EQUATION FOR OGEE SPILLWAY
what is c4x light weight cement blocks
what is the formula for Mass of cement grout (Dg)=???
How much permissible bearing capacity requires for open footings(isolated) and what type pile foundatuon prefering for coastal areas?
What are the advantages of building a dam on the river nile?
insted of bentonite we can use any alternate material in piling ?
usually hand broken stones are used for cement concrete 1:4:8 in foundation of single /two story houses with a view of economy in construction.what advantages it will give if you use machine crushed stone in place?
What is absolute pressure? How absolute pressure is calculated?
04. a. Slenderness ratio…………… 1 b. If the height of a stage is 15-0 & dia. of the prop is 5, the slenderness ratio is….… 1 c. If the height of a stage is 10-0 & dia of prop is 3, the number of bracing will be…… 1
Rate analysis of 150mm, 100mm, & 230mm thk BBM work
How to arrive d*d/162 , for finding the kg per meter , wt of steel
100mm block work 64 bags of cement used 150mm block work 286 bags of cement used 200mm block work 20 bags of cement used patly work (M15) 293 bags of cement used mortar ratio is 1:5 how to calculate volume of sand in cum & no. of bags