Do you have different BOMs for a material in different plants?
Answers were Sorted based on User's Feedback
Answer / jinchandramule
Yes,
we can have more than one BOM FOR A MATERIAL in Different
plants.
Depending on the plants reqts and the components
requirements,as well as the alternative requirements .
Is This Answer Correct ? | 15 Yes | 1 No |
Answer / darshan dave
Yes we can have Different BOMs for a material in different
plants.
Is This Answer Correct ? | 12 Yes | 2 No |
Answer / bharat patil
yes, we can create plant specific boms for same material.
Is This Answer Correct ? | 6 Yes | 0 No |
Answer / santosh sharma
well,
we have different BOM for different-different plant.
because in another plant there are differet material
sothat there are create the BOM's different types.
Is This Answer Correct ? | 5 Yes | 0 No |
Answer / abhijit guharoy
generally we have following BOMs
1.Product Tree
2. Parent- component relationship
3. Multilevel Bill
4.Multiple Bill
5. Single Level Bill
6. Indented bill
7. Summarized parts list
8. Planning bill
9. where- used report
10. Pegging report
Is This Answer Correct ? | 3 Yes | 1 No |
Answer / siddharth
yes ofcourse for particular material there can be different
BOMs at plant level becoz components consumed might be
different at any other plant.
Is This Answer Correct ? | 1 Yes | 1 No |
why their is need of production version
How to create prt master records?
Difference between MTO & MTS
1 Answers Cognizant, UT Pumps,
How is the processing time calculated in a wc when both labor, machine categories exist?
One component 2 times assign to bom
Explain source inspection.
What are the different type of BOM usage?
when we need to close the production order, before the manufacturing or after the manufacturing
explain Group and recursive bom
Difference between byproduct and co-product.
Why is work scheduling required for semi finished and finished products?
Once the Production order is created, how to change the BOM and routing in that order?