Do you have different BOMs for a material in different plants?
Answers were Sorted based on User's Feedback
Answer / jinchandramule
Yes,
we can have more than one BOM FOR A MATERIAL in Different
plants.
Depending on the plants reqts and the components
requirements,as well as the alternative requirements .
Is This Answer Correct ? | 15 Yes | 1 No |
Answer / darshan dave
Yes we can have Different BOMs for a material in different
plants.
Is This Answer Correct ? | 12 Yes | 2 No |
Answer / bharat patil
yes, we can create plant specific boms for same material.
Is This Answer Correct ? | 6 Yes | 0 No |
Answer / santosh sharma
well,
we have different BOM for different-different plant.
because in another plant there are differet material
sothat there are create the BOM's different types.
Is This Answer Correct ? | 5 Yes | 0 No |
Answer / abhijit guharoy
generally we have following BOMs
1.Product Tree
2. Parent- component relationship
3. Multilevel Bill
4.Multiple Bill
5. Single Level Bill
6. Indented bill
7. Summarized parts list
8. Planning bill
9. where- used report
10. Pegging report
Is This Answer Correct ? | 3 Yes | 1 No |
Answer / siddharth
yes ofcourse for particular material there can be different
BOMs at plant level becoz components consumed might be
different at any other plant.
Is This Answer Correct ? | 1 Yes | 1 No |
What is scheduling
Explain what is the meaning of exploding a bom?
Suppose the client wants me the vacancy to be displayed on a website as well as ess. How should I do it?
What is purpose of schedule margin key?
What is planning file entry and Where can we use
What do you mean by pooled capacity?
Define stock requirement
How to move to the realization phase?
You want to insert an inspection check point at the end of an operation. How would you do that?
Different types of consumption based planning.
Explain LTP.
What is MPS and difference between MRP and MPS?