give me the mix proportion for design mix concrete M10 grade
1:4:8
Answers were Sorted based on User's Feedback
Answer / hari haran
its cement:fine agg:coarse agg
if we take 1 bag of cement=50 kg
then
cement=50 kg
fine agg=50*4=200kg
coarse agg=50*8=400kg
water cement ratio=0.4
w/c=0.4*50=20 liters of water
| Is This Answer Correct ? | 95 Yes | 23 No |
Answer / arun kumar
ITS MEAN 1:4:8
CEMENT:SAND:COARSE AGGREGATE
MEANS 1 BAG OF CEMENT, 4 BAGS OF SAND, 8 BAGS OF COARSE
AGGREGATES
| Is This Answer Correct ? | 72 Yes | 17 No |
Answer / prashant rawat
M10 grade Ratio is 1:3:6 And 1:4:8 is M7.5
| Is This Answer Correct ? | 49 Yes | 11 No |
Answer / nimmakayala
It not a design mix
It is a lean mix of proportion is 1:3:6(C:FA:CA)
| Is This Answer Correct ? | 29 Yes | 2 No |
Answer / orient builders
1 4 8 means cement sand (fine aggregate) metal 20 mm (coarse
aggregate)respectively.
The ratio is based on volume and not in weight.
one bag of cement is 1.25 cubic foot
Therefore multiply the fine and coarse aggregate with 1.25.
Thus you have to use 1.25 cft of cement (one bag) and 5 cft
of sand and 10 cft of coarse aggregate.
As for sand is concerned bulkage allowance is to considered
according to which the quantity may slightly vary
| Is This Answer Correct ? | 23 Yes | 4 No |
Nominal mix propertion of M10 PCC grade is 1:3:6 & Nominal
mix propertion of M .75 Is pcc grade for 1:4:8
Normally Mix design consider for above M20 grade as for Is
code 456
| Is This Answer Correct ? | 18 Yes | 4 No |
Answer / sunil1505
its not a design mix. after m25 that called design mixes...
1:4:8 cement,sand,aggregate..water ratio is 0.4
m7.5 1:6
10 (1:4:8 and 1 :3:6)
15 1:2:4
20 1:1.5: 3
25 1 : 1 : 2
| Is This Answer Correct ? | 9 Yes | 2 No |
Answer / kumar s
For M-10 grade nominal mix design is 1:3:6
For M-7.5 grade nominal mix design is 1:4:8
As per IS 456:2000, Nominal mix concrete may be used for concrete grades M-20 or lower. Design mix can be arrived with several trial mix design as per guideline proposed in IS 10262:2009. Example my trail design mix for M 10 is 1:3.5:6.10
Hope this will be useful for you...
| Is This Answer Correct ? | 7 Yes | 0 No |
relation bet Coefficient consolidation Cv, time factor Tv, drainage path d, & time t is Cv=d2Tv/t Cv=d2t/Tv Cv=tTv/d2 Cv=Tv/td2
What is the standard brick size in India(IS)
what is procedure to find the volume of material in M20 concrete?
what is the full form of GGBS?
What is the difference between auto & dumpy level
Calculation of Pier Cap with tapper area?
whatis the banafit of water leak detection and repair?
How to hide dimensions in autocad?
what is the process of repair the structure in whitch reinforcement is open
what is superbuilt-up area in flats & how it is calculate?
what is lap length? why it is required?
how to find number of 16mm bar reqired for 5m length with 125 mm spacing ?
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)