Answer / priya
In the construction of RC buildings, due to the
limitations in available length of bars and due to
constraints in construction, there are numerous
occasions when column bars have to be joined. A
simple way of achieving this is by overlapping the two
bars over at least a minimum specified length, called
lap length. The lap length depends on types of
reinforcement and concrete. For ordinary situations, it
is about 50 times bar diameter. Further, IS:13920-1993
prescribes that the lap length be provided ONLY in the
middle half of column and not near its top or bottom
| Is This Answer Correct ? | 28 Yes | 2 No |
Answer / sjtbehera
Lap length are recquired when distance of structure is
larger than the length of Bars.
It is recquire to bind the two bars so that load can
carried.
| Is This Answer Correct ? | 6 Yes | 4 No |
Lap Length is 3/2 lap Lenths. Depends on Road
Length.Methods are 3/2. ItS Reqiured is very impotant
Reniforcement continous.
| Is This Answer Correct ? | 2 Yes | 9 No |
How many materials e.g bricks, cement, sand, stone required to build a house for 100 sqft
How much steel and concrit required in 1000 square feet slab?
what is the procedure for flakiness and elongation index
What is the use of offset command?
what is plate load test and what is the procedure of it and what is accessories which in use
How to Concrete cube test method and required result in 3days & 7days & 28 days, for all grade of concrete which refer the is code no.
how many type of admixtures for water stored structure?
what is mix design of sand cement and and aggrigate of M10 M20 M25..
why 50% more is assumed while calculating dry volume of coarse and fine aggregates in concrete calculations.whether 50% more is correct? How is it decided? whether the same is applicable to cement volume. Also what about cement mortar dr volume? How much more is to be considered for dry volume of mortar.
plumbing CPVC fitting FTE Brass full form
what is calculation of cement, snd of 1:4 16mm,12mm plastring
"Gates of the dams are generally designed of curved shape". Why?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)