Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


how many days we should curing for
plastering,brickwork,concrete?

Answers were Sorted based on User's Feedback



how many days we should curing for plastering,brickwork,concrete?..

Answer / senthil kumar p

Any cement based products or structures the minimum curing
period is 7 and maximum 28 days for concrete unless
otherwise you are using any curing
compound

Is This Answer Correct ?    115 Yes 6 No

how many days we should curing for plastering,brickwork,concrete?..

Answer / jai.vignesh

Any cement based products or structures the minimum curing
period is 7 days unless otherwise you are using any curing
compound

Is This Answer Correct ?    79 Yes 8 No

how many days we should curing for plastering,brickwork,concrete?..

Answer / s

7day min

Is This Answer Correct ?    43 Yes 5 No

how many days we should curing for plastering,brickwork,concrete?..

Answer / ganesh mapari

7 Day for Brickwork and Plastering
14 Days for Concrete

Is This Answer Correct ?    36 Yes 3 No

how many days we should curing for plastering,brickwork,concrete?..

Answer / venkataratnam.y

minimum 7days

Is This Answer Correct ?    21 Yes 3 No

how many days we should curing for plastering,brickwork,concrete?..

Answer / udaya

It is 14 days normally. Normally we follow 14 days in summer
and 7 days in winter

Is This Answer Correct ?    24 Yes 7 No

how many days we should curing for plastering,brickwork,concrete?..

Answer / ram mohan rai

Curring should start as soon as concrete start hardening
till at least 7 days depend upon weather condition.

Is This Answer Correct ?    12 Yes 0 No

how many days we should curing for plastering,brickwork,concrete?..

Answer / engr.sameer

concrete need min 7 days contineous curing

Is This Answer Correct ?    12 Yes 0 No

how many days we should curing for plastering,brickwork,concrete?..

Answer / naveen

28 days.

Is This Answer Correct ?    20 Yes 21 No

how many days we should curing for plastering,brickwork,concrete?..

Answer / muraliyadav

This is
depending upon
the structural
element as well
as depends on
the type of
cement can be
used in
construction
site works .the
minimum 7days
required for any
structural
element as
beams,columns,slabs
in these days
concrete did not
get full
strength only
upto 25%, if 28
days required
strength as 70
to 80% of
concrete

Is This Answer Correct ?    10 Yes 12 No

Post New Answer

More Civil Engineering Interview Questions

what is the procedure to clean the mivan technically?

1 Answers  


how much nails used in 1 sq m shuttering

16 Answers   L&T, Pearls, Simplex,


Kindly post me previous year interview questions with answer for post of DY. Manager (civil engg.) for GAIL, NTPC, IOC, OIL and ONGC etc.

0 Answers   GAIL, KOC, Megha Constructions,


Laboratory experiments conducted in Mumbai on a particular mix showed a strength of 33 MP a for a fully matured concrete. Find whether formworm can be removed for an identical concrete placed at Jammu at the age of 15 days when the average temperature is 60C. The stripping stress in concrete

2 Answers   CCIL,


HOW YOU CAN DETERMINE THE WEIGHT PER METER OF STEEL RODS EASILY?

18 Answers   Arabian Pipes,


Under what circumstances should pot bearings be used instead of elastomeric bearings?

0 Answers  


100 cubic meter of concrete will contain how much amount of cement, sand and aggregate to form a mix of M15

5 Answers  


how many average of shuttering in one cubic meter concrete

5 Answers  


Are you having any structural design experience?

4 Answers   Ajnara Group, Jeyam Homes, L&T,


How to ascertain the required grade of Steel is good for Site .....

1 Answers  


What isthe formula for square

1 Answers   Panchayati Raj Department,


in the footings first which reinforcement bar has to be layed as per design criteria.

3 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4453)
  • Electrical Engineering Interview Questions Electrical Engineering (16638)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)