how many average of shuttering in one cubic meter concrete
Answers were Sorted based on User's Feedback
Answer / v.kapil
i understand your problem
if you want to calculate shuttering in a genral rasidential
building so you can consider 5-6 Sqm / Cum of conc. but
when you talking about foundation it reduced up to 2-3 Sqm/
Cum, ultimatly there is no as such thumb rule but we can
adopt a value by our experience...
Is This Answer Correct ? | 57 Yes | 6 No |
Answer / ilias mahammad
Shuttering Qty can be taken as approx.5-6 times the volume
of concreting.
i.e. for 1 cum of concreting approx. 5.00sqm-6.00sqm
shuttering is required.
Is This Answer Correct ? | 19 Yes | 3 No |
Answer / sjtbehera
look shuttering are done to cover the concrete to a
minimum period so that it will become hard. it's
calculation are done by sqft or sqmt. for one cubic mt
concrete it can calculate by covering the area of structure
in length x breadth or height.
Is This Answer Correct ? | 21 Yes | 9 No |
Answer / mrinal bose
Approximate Shuttering value 1:8.88 it is standard shuttering volume. The standard column size 300 mm X 450 mm, Slab thk is 125 mm, plinth beam 230 mm X 350 mm, Beam/ slab beam 230 mm X 450 and foundation shuttering will less then above average shuttering quantity 8.88 Sqm per cubic meter
Is This Answer Correct ? | 4 Yes | 2 No |
Answer / dalip kumar
for shuttering point of view, there is area of concrete work is important rather than it's volume, e.g. 1 c.m concrete
can be spread on the 2 sq.m and 1 sq.m that is why it design by covering area of the concrete.
Is This Answer Correct ? | 2 Yes | 17 No |
rate of 1cum brick masonry please immidate
How to calculate the dia of reinforcement when required (as per drawing) dia of reinforcement steel not available at site?
3 Answers MNC, N J Devani Builders, Simplex,
Which is the indian standard code of line out. ? How much tolerance fot 1 mt lenght? Its challenge....
how to balance aggregate during mix design of concrete???? how to calculate moisture content like C/A,F/A and how many percentage using ice instead of water for example of we are preparing ice concrete??????
how we can prevent freshly laid concrete from rain ,, What the plastering thickness for a) inner brickwork b) outer brickwork c) beams & slabs
In the different classes or grades of concrete, what is the difference between C20, M20 B20. what are the letters C, M, and B stands for.
how to calculate shuttering measurement of beam and slab
how to calculate the 45 degree bent up length. if we given that whether the total length of the slab reinforcement will increase or not. mantion it clearly please. this is for bar bending schedule purpose?
WHAT IS THE CAUSES OF RUTTING ON FLEXIBLE PAVEMENT?
0 Answers Ace Info, Anil Group,
how much quantity of cement bags are required to fill the one m3 of empty container.?
How to find the requirement of cement and sand for the 1cum of rr masonry work
how to convert kg/m3 to kg/cft