how many days we should curing for
plastering,brickwork,concrete?
Answer Posted / udaya
It is 14 days normally. Normally we follow 14 days in summer
and 7 days in winter
| Is This Answer Correct ? | 24 Yes | 7 No |
Post New Answer View All Answers
explain five benefits of using standard terminology in the measurement process?
How foundation is designed, Column design and beam design
Method of findingthe dry ingredient quantity of 1 m3 concrete. what is the difference between static and dynamic induced emf? Testing charges bill given for Rs. 32,000/- but not added service tax in this bill. So, How much TDS will be deduct
what is the max. area can we apply the plate load test ?
How we calculate the service time of buildings
What is type failure of road surface? how to repair the failure of road surface?
Draw the cross section of a boundary wall and label its part with detailing?
How its coming concrete grade M 20 means 1:2:4. how it coming 1:2:4.
Define Workability ?
How much cement will require for 1Rmt Skirting laying
how much area can be platered by a mason for exterior
Mention different types of roof systems?
Why you are leaving present job?
What happens to Load at yielding ?
what is the difference between prime coat and tack coat in road construction