100 cubic meter of concrete will contain how much amount of
cement, sand and aggregate to form a mix of M15

Answers were Sorted based on User's Feedback



100 cubic meter of concrete will contain how much amount of cement, sand and aggregate to form a mi..

Answer / yogesh jadhav

m15(1:2:4)
100cum given
wet volume of concrete=30%more than dry volume
=1.3*100=130cum
wastage=20%of wet volume of concrete
=1.2*130=156cum
volume of cement required=156cum/1+2+4=22.28cum
1 bag of cement=35 lit=0.035cum
no of cement bags required=22.28/0.035=636.57=637bags
sand rqd=2*22.28=44.56cum
coarse agg reqd=4*22.28=89.12cum

Is This Answer Correct ?    24 Yes 5 No

100 cubic meter of concrete will contain how much amount of cement, sand and aggregate to form a mi..

Answer / sjtbehera

For3 100 cum

Aggregated- 88 cum

Sand-44 cum

Cement- 22cum. 660 bag

Is This Answer Correct ?    18 Yes 7 No

100 cubic meter of concrete will contain how much amount of cement, sand and aggregate to form a mi..

Answer / channa

1m3 of dry concrete = 1.54m3 of wet concrete
Concrete work to be done=100×1.54=154m3
Cement=(1/(1+2+4))×154=22m3
Wkt, density of cement=1440kg/m3
Mass of cement=1440×22=31680kg
No of cement bags= 31680/50=634bags of cement required

Is This Answer Correct ?    3 Yes 0 No

100 cubic meter of concrete will contain how much amount of cement, sand and aggregate to form a mi..

Answer / vishamvar

For 10cum of M15 (1:2:4)
concrete 15.2cum dry weight
is require thus
for 100cum concrete
approx. Quantity of material
will be

Cement = 21.71 cum
Sand = 43.43 cum
Aggregate = 86.84 cum

Is This Answer Correct ?    5 Yes 3 No

100 cubic meter of concrete will contain how much amount of cement, sand and aggregate to form a mi..

Answer / ajit kiling

For 100 cum work
For m15 grade of concrete (1:2:4)
Dry mortar of 1cum =1.54cum For 100cum= 100*1.54
= 154cum
Cement=154/(1+2+4) = 22cum
Sand= 22*2=44cum
Aggregate=22*4=88cum

Is This Answer Correct ?    2 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

what will be the total emoluments for deputy surveyor in APPSC in the payband of ( 9460-27600). please give me the detailed information step wise?

0 Answers   APPSC,


1) a)to prepare mortar for bricklaying how much amount of water should be added for its maximum strength and workability(to avoid cracks which results, when high quantity of water is added)?is their a formula or ratio? b) suppose we want to make 1:3 mortar,what is the best way to measure cement ,sand and water and how? c)time before which freshly prepared mortar should be used? d)proper way to mix and make mortar? e)when should curing start after laying bricks and for how long?and also how many hours per day? f)what is shear wall (please in terms of layman lol) bookish definisions are confusing.... g) and last,acc to codes what are max no. of course that should be laid in a day.

0 Answers  


Strength of brick?

2 Answers   YSB,


What Are The Steps Involved In The Concreting Process, Explain?

0 Answers   Bechtel,


what is the basic difference between Coloumn & Shear Wall

0 Answers  






What the approval that owner will give to contractor during construction project period? What will the affect on project if delays due approvals?

2 Answers  


how much the volume of one packet cement ?

6 Answers  


The definition of national highway

0 Answers  


what is period of de-shuttering for different area of slab of M25 grade?

2 Answers   ATS,


PERT Chart

1 Answers  


What is the standard specification of MOR and Water Absorption of Homogenous Ceramic Floor Tiles?

0 Answers  


What is the diff between cad & cadd?

0 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4452)
  • Electrical Engineering Interview Questions Electrical Engineering (16638)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)