suppose, concrete mix ratio = 1:1.5:3
then, sum = 1 1.5 3 = 5.5
as we know,dry material required for 1 cum. of concrete =
1.54 cum.
then we can find -:
(1) cement = 1*1.54/5.5 = .28 cum. or .28cum.* 28.8= 8.06
bags.
(2) sand = 1.5* 1.54/5.5 = .42 cum.
or .42cum.* 35.3 = 14.83 cubic feet.
(3) coarse aggregate = 3* 1.54/5.5 = .84 cum.
or .84 cum.* 35.3 = 29.65 cubic feet.
so, dry ingredient quantity required for 1 m3 of concrete-:
cement = 8.06 bags.
sand = 14.83 cft.
coarse aggregate = 29.65 cft.
Is This Answer Correct ? | 0 Yes | 0 No |
Answer / waqas ahmad
it is the 54% of dry volume
1m3 wet volume = 54% dry volume
1 :1.5 : 3
1+(54%) x 1= 1+0.54 = 1.54
cement = (1x1.54) / 5.5
sand = (1.5x1.54) /5.5
aggregate = (3x1.54) /5.5
Is This Answer Correct ? | 0 Yes | 0 No |
What is PCO
Using 1 lit paint how many sq.ft of wall we can paint. Thanks.
what is the measure of slump
What is a MIS report?
How to calculate Volume of Wet cement concrete for a specific grade?
Draw a neat sketch showing the 'throat' of a welding in a plate girder ?
how to calculate steel quantity of column from steel design
what is rigid pavement
how to calculate the quantity of steel in a slab , beam and coloumn
1 building project (work in progress) and following are sum detail about his project 1) Using local rebar grade 415 2) Total built up area- 60000 sq.ft 3) Floors to be constructed – 21 storey 4) Estimated requirement of Steel per sq. foot – 7KG/sq.ft 5) Concrete grade – M35 6) Rebars mainly required (sizes)- 16,20,25,32 & (8 mm for stirrups) Wanted to ask u if this person uses 500D…what are the benefits he will be getting? Whether his per Sq. foot consumption can b reduce? If yes den around how much?
contractor receive 100 MT steel.after compliting the work the contractor refund 90 MT steel.How reconsilation of steel done?
what is meant by GANTRY GIRDER?