Why we do design mix of concrete when there is nominal
method using the IS-Code available ?

Answers were Sorted based on User's Feedback



Why we do design mix of concrete when there is nominal method using the IS-Code available ?..

Answer / mallikarjuna (nitw)

to ensure required |Target Mean Strength by controlling the
parameters of aggregate,sand and water accurately ....n
also to design higher grade of concrete ...

....incase of nominal mis method(say),M15 means 15mpa
comp.srength on 28 days using 1:2:4 proportions without
considering various conditions of conareting
materials ...the same will be rectified in design mix .

simply nominal mix is blind technique where as design mix
is live n vibrant method of mix design in concrete
technology to achieve anticipated TMS.

Is This Answer Correct ?    46 Yes 3 No

Why we do design mix of concrete when there is nominal method using the IS-Code available ?..

Answer / aasinghai

to achieve economy and safety

Is This Answer Correct ?    34 Yes 4 No

Why we do design mix of concrete when there is nominal method using the IS-Code available ?..

Answer / arunkumar.t

to save an optimum content of cement, from 7.5 to 8 bags of
cement to 6.6 bags of cement per CuM

Is This Answer Correct ?    28 Yes 11 No

Why we do design mix of concrete when there is nominal method using the IS-Code available ?..

Answer / sudheer

To acheive best possible concrete with the ingredients
available at particular location design mix is used.

Is This Answer Correct ?    17 Yes 1 No

Why we do design mix of concrete when there is nominal method using the IS-Code available ?..

Answer / santosh

design mix of concrete give the exact quantity of material
such as cement, sand, aggregate & water.so that economy in
the material can be possible. higher strength of concrete
can be achieved with min. content of admixtures

Is This Answer Correct ?    12 Yes 0 No

Why we do design mix of concrete when there is nominal method using the IS-Code available ?..

Answer / nagori salim

The basic difference betn the two is;

Nominal - Volumetric Batching.

Design - Weight Batching.

In design mix degree of quality & control on quantity is
highly maintained.

Is This Answer Correct ?    12 Yes 2 No

Why we do design mix of concrete when there is nominal method using the IS-Code available ?..

Answer / subhendu,jadavpur

In the code specified ratio there is no any consideration
of workebility, which in one of the mandetory aspects to be
considered. But by mix design we can design the concrete of
required workebility without sacrificing the strength.

Is This Answer Correct ?    8 Yes 1 No

Why we do design mix of concrete when there is nominal method using the IS-Code available ?..

Answer / raju mandal

Because the properties of available material is varies from
site to site.It is preferable because we want to get
strength of concrete at optimum cost.You can use nominal
method of mix if you are able to provide standard
characteristics to the all material.

Is This Answer Correct ?    7 Yes 1 No

Why we do design mix of concrete when there is nominal method using the IS-Code available ?..

Answer / sailesh kaw

Design mix is carried out for the optimization of concrete,
to increase its durabilty and to decrese its permeability.
WC ratios is also reduced.

Design mix is based on the specific weights of the material
where as 1:2:4, 1:3:6 etc are volumetric based design

Is This Answer Correct ?    7 Yes 2 No

Why we do design mix of concrete when there is nominal method using the IS-Code available ?..

Answer / rakesh kumar mallik

By design mix of concrete we can achieve more workable
concrete without hampering the strength of concrete which is
not possible in nominal mix of concrete.
By design mix we have have control over the quantity of
material,water cement ratio to achieve the required strength.

Is This Answer Correct ?    0 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

What is the quantity of cement, sand, and gravel to be used in M20 grade of concrete for 1000 x 1000 x 1000 mm of sand (for cement please mention in kilos, and for sand and gravel please mention it in CFT)

7 Answers  


what is the venturi effect in buildings? what is green house concept?different types of dams? which dam is economical arch dam or gravity dam. what are the conditions favourible to both of them?

0 Answers  


What is the unit weight of cement,sand,Brick,Reinforcement concrete

1 Answers   L&T,


what happened if the diameter of capillary tube is double then the capillary rise will be

7 Answers   Bhel,


How you can turn off the display for dimension in CAD?

0 Answers  






What is meaning of Canceled/Flat Beam. What is difference between them? Both type of beam can bear same load if size (width)of the flat beam is increases and depth is same as slab thickness? Kindly suggest to me.

0 Answers  


what is density of flyash?

5 Answers   ACS,


how much quantity of cement and sand required for construction of 10 cum brick work( Brick size 3"*4"*9"(Standard size ) an d for 10 cum construction of SSM (Size stone masonary) with Cm 1:6 for both.

11 Answers   GRC, KEC, L&T, Techno Electric and Engineering, UPENN,


1:6 mortar, how many self life hours ?

4 Answers   CCCL, L&T,


if we get water mor from 28 days to the rcc concret is this better or have a damag

3 Answers  


What is Lap Length??????

24 Answers   CCCL,


1sqm tile laying how much cement required?

2 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)