Answer / praneeth
Max cement use dfor 1 m3 of concrete is 450 kgs.
if we consider normal w/c ratio as 0.4
Max water required becomes 450*0.4=180 litres of water
| Is This Answer Correct ? | 45 Yes | 9 No |
Answer / abhishek
Say 1 m3 = 450 Kg Cement
Now, Considering W/C ration as 0.45
Water = 450 x 0.45 = 202.5 Litres
| Is This Answer Correct ? | 13 Yes | 7 No |
Answer / vivek tripathy
In 1 cum of concrete we require 350kg of cement .Considering the water cement ratio is 0.5 ,so water required is 0.5*350= 175 liters
| Is This Answer Correct ? | 5 Yes | 5 No |
for what perpuse we use CBR test in road project?
what is the breaking strength of wall tiles
how we check the thickness and line of ceiling plaster.
Is 456 revised lastly in which year? & What are the revisions?
What is the diffrence between plinth/basement and plot area
Define What is an ice dam sock?
what is the metal ratio in granular subbase coarse for one cum ? And please explain the morth table ...what is the difference between grading 1 , 2, 3 what it means..plz explain
appsc AEE'S interview questions wanted
M40 grade concrete has 40 n/mm2 strength.here what"s mean by n?
200mm*200mm thick block work 1sqm how many cement bags
give me the mix proportion for design mix concrete M10 grade 1:4:8
13 Answers Gammon, IOCL, PSL, SDG, Simplee, STUP Consultants Pvt Ltd,
What is the meaning of M50,20? What is 50,what is 20
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)