how many liters of water required for 1cu.m concrete? ..

Answer / praneeth

Max cement use dfor 1 m3 of concrete is 450 kgs.

if we consider normal w/c ratio as 0.4

Max water required becomes 450*0.4=180 litres of water

Is This Answer Correct ?    45 Yes 9 No

how many liters of water required for 1cu.m concrete? ..

Answer / abhishek

Say 1 m3 = 450 Kg Cement
Now, Considering W/C ration as 0.45
Water = 450 x 0.45 = 202.5 Litres

Is This Answer Correct ?    13 Yes 7 No

how many liters of water required for 1cu.m concrete? ..

Answer / vivek tripathy

In 1 cum of concrete we require 350kg of cement .Considering the water cement ratio is 0.5 ,so water required is 0.5*350= 175 liters

Is This Answer Correct ?    5 Yes 5 No

Post New Answer

More Civil Engineering Interview Questions

Sir your company in receiver ment of civil engineering.

1 Answers   Amrapali,


what is the curing time for plastring (all)?

2 Answers  


How to take labor charges for construction of 1cum of concrete?

0 Answers  


In reclamation works what are the importance of geotextiles and sand?

0 Answers  


Name the main components of a cad gui?

0 Answers  






1cubic meter of bricks = ? kg

1 Answers  


how to calculate cut length of re-bar in a circle . because we not place same length of re-bar in whole circle maximum in center and minimum at corner so how to calculate middle bars???

0 Answers   Student,


What are the specification of good quality sand for plaster and brickwork?

2 Answers  


how many material required for brickbat water proofing of toilets.

0 Answers   DLF, Harpic,


what is the defination of an ideal fluid?

7 Answers   NTPC,


Design a built-up column carrying an axial load of 1200 KN. Its length is 8m and it is effectively held in position at both ends and restrained against rotation at one end. Assume yield stress of 250 mpa

0 Answers  


How to identify the vitrified tile and ceramic tile by observation only after executing the job.

0 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4452)
  • Electrical Engineering Interview Questions Electrical Engineering (16638)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)