How can we shut off the "automatic costing indicator" and
the "automatic scheduling indicator" which go on when the
production order is released?
Answer / guest
For "no automatic costing" follow the IMG path
Production -> Production orders ->Master data -> Order ->
Define order type dependent parameters
Select the order type for which u automatic costing is
not required. In the controlling settings, select "no
automatic costing"
For "no automatic scheduling" , follow the IMG path :
Production ->Operations - >Scheduling -> Define control
parameters
Select the order type and go to details. Deselect "
automatic dates "
Alternatively, you can find indicators in the control
key, which is in the routing. Transaction OPL8 gives you costing
indicators (Order type dependent parameters), and OPJU
(control table for scheduling) gives some scheduling options.
Is This Answer Correct ? | 1 Yes | 2 No |
What is planning file entry
What is 'mps' (master production scheduling)?
If I need to maintain a PP module in SAP from the information received from another system, Can i use a table to create the data required for creating the PP
Integration between PP and PM module.
what is the need of pp in sap, what is the flow diagram of sap pp.
What is the data you give in SOP
What is meant by payscale structure? How did you configure the payscale structure?
How to create PRT master record?
How costing is affected the pp?
If process order is technically closed, by mistake I want to process that order again can I do it?
What is the use of mrp list?
Do your single-level BOMs represent production levels and do you keep your BOM header materials in stock? If not, do you produce non-stock items, or are some assemblies just used as structural elements in a BOM?