explain BOM usage and status?
Answers were Sorted based on User's Feedback
Answer / rasika deshpande
By means of BOM usage, you can manage separate bills of
material for various internal organizational areas
(engineering/design, production, costing, and so on).We can
define different boms for the different areas of the
company, such as design dept, production, sells and
distribution etc. , depending on their individual
requirement. This can be done by choosing different usages
while creating the bom.
The BOM status specifies whether a bill of material is
active or inactive for different organizational areas.
it can be seen at header level of the bom.
Is This Answer Correct ? | 13 Yes | 4 No |
Answer / atul y
The bill of material usage specifies the departments or
functions within a company where the bill of
material is used.
The BOM status controls BOM processing in different
application areas
Example:
BOM X:
BOM with status '1' can be exploded in MRP and released for
a planned order.
BOM Y:
BOM with status '2' cannot be exploded in MRP or released
for a planned order.
Is This Answer Correct ? | 5 Yes | 1 No |
Answer / venkatesh
Bill of Material is the quantity details of each item used
for producing a finished product.
Is This Answer Correct ? | 1 Yes | 4 No |
while extending the material master view after saving error is coming that the field material number is defined as a required field,it doesnt contain an entry. After selecting that it is showing the particular material may be locked. Pls do the needful.
• How are basic order dates determined?
What is MRP group?
What happens to planned after it has been converted into production order ?
what is group bom? Is it possible to attach the drawing for a material to bom? How?
What is the recruitment cycle?
any one can provide me some sample resume for SAP PP with 0 to 1 year experience?
Difference between Routing, Ref op set, Rate routing and Ref rate routing.
What is the uses of production scheduling profile and what the configure have you done current project
0 Answers Cognizant, Patanjali Ayurved,
What are all the steps involved in Variant Configuration?
Do you have different BOMs for a material in different plants?
What parameters you maintain in “plant parameters” in configuration?