How do we calculate the building footing calculation ?
Answers were Sorted based on User's Feedback
Answer / ds raju
Question is not clear. Is it design calculation ? or RCC
volume of the footing.
Design calculation depends on the safe bearing cpacity of
the soils and load on the footing.
Concrete volume can be calculated based on the shape of of
the footing.
For Rectangular/ square type : LxBxH
For Trepezoidal type : h/3 (Area at bottom-A1 + Area at top-
A2 +SqRt of (A1xA2)
Is This Answer Correct ? | 36 Yes | 2 No |
Answer / r.vandhana
the calculation varies for each type of footing
Is This Answer Correct ? | 24 Yes | 4 No |
Answer / sachin kesarkar
FOR RECTANGULAR FOOTING VOLUME= L*B*H
WHERE L=LENGTH B=BREDTH H=HEIGHT
FOR TRAPEZOIDAL FOOTING VOLUME=h/3(A1+A2+ROOT A1.A2)
WHERE h=HEIGHT A1=TOP SURFACE AREA A2=BTM.SURFACE AREA.
THERE ARE ALSO THE FOOTINGS WHICH ARE NOT PERFECTLY
TRAPEZOIDAL, IN THAT CASE WE HAVE CALCULATE IT WITH
TRAPEZOIDAL HAVING 5% VARIANCE.
Is This Answer Correct ? | 20 Yes | 4 No |
Answer / srinivasan
1) FOR RECTANGULAR OR SQURE PORTION L X B X H WHERE L=
LENGTH B= BREADTH, H= HEIGHT
2) TRAPEZOIDAL PORTION H/3 (A1+ A2)+SQRT (A1*A2)
Is This Answer Correct ? | 9 Yes | 2 No |
Answer / guest
width of footing can be calculated as
w= 2*l + 30
depth of footing can be varied as soil change
Is This Answer Correct ? | 3 Yes | 9 No |
Answer / guest
Dear friends generally we do this footing calculation like
this two method =
(A)1st method =i)1.500 m x 1.500 m x 0.500 m = 1.13 Cum.
ii)½ x ( 1.500 m + 0.250 m ) x 1.500 m x 0.200 m = 0.260
Cum. (B)2nd Method =i)(1.500 x 1.500 x 0.200)+ (0.250 x
0.250 x.0.250)= 0.460 Cum.
ii) ( 1.500 x 1.500)+ ( 0.250 x 0.250)/2 x 0.200 = 0.231
Cum.
( But I think it is not proper procedure so please you do
properly )
Is This Answer Correct ? | 10 Yes | 33 No |
what is the meaning of degreasing of the euipment or line.
what is the yield strength of M30 grade of concrete
How can i find number of brichs required for given quantity of wall in m^3..
5 Answers vasanth construction,
Is there any codal provision stating the actual diameter for chair bars?
What are the different grades of concrete & their ratios?
Differentiate first angle & third angle projection?
suppose that 156000 sq.ft rcc work builtup are.how many % of brick work to rcc work.
How much lap length provided in compression and tension in bridges?
Wat is the optimum value of tensile strength of concrete after 28 days?
if size is 235cmsx15cmx100cms so how many cement bags and how many sand bags are used for concrete mix
0 Answers Ras Engineering, UltraTech,
While calculating quantity of cement required for 1 qubic meter If mix is m25 1:1:2 =4 1.52/4=0.38, 0.38x1440=547.20 kgs I know 1440 is unit weight of cement And what is 1.52 ? And some one using 1.54 and 1.53 etc... Why they are using can u explain me what is 1.52, 1.53, 1.54?
for G+2 residential building how much quantity of required in foundations,sub & superstructures per sq ft area