a)If column dimensions are 250*400mm , what will be
cutting length for 8mm stirrups and how to calculate it? b)
If beam dimensions are 200*400mm , beam coveris 25mm , slab
cover is 20mm , what will be the cutting length for
stirrups? c)Column dimensions are 250*400mm , reinf. is
12nos. bar of 16mm dia , stirrups provided are two legged,
what will be the length of each ring?

Regards

Answers were Sorted based on User's Feedback



a)If column dimensions are 250*400mm , what will be cutting length for 8mm stirrups and how to ca..

Answer / dhivakar

(2A+2B)+8*d
2(320+170)+64 =1044m

Is This Answer Correct ?    1 Yes 3 No

a)If column dimensions are 250*400mm , what will be cutting length for 8mm stirrups and how to ca..

Answer / er shailesh kr srivastava

A)CUTTING LENGTH FOR 8mm Strips=2(250+400-2*80-2*8+24*8)
2(650-160+22*8)
2(490+176)
=1332mm

same as for beam

Is This Answer Correct ?    6 Yes 9 No

a)If column dimensions are 250*400mm , what will be cutting length for 8mm stirrups and how to ca..

Answer / ajay

sir , my name ajay kumar ,working on site i also had the
same problem of estimation , but sir ur answer was so nicely
explained , im very thank full to u for ur valuable and
precious information, sir can i no ur email id and no so i
can get some knowlege from u ?
my email -ajaykapse2@gmail.com

Is This Answer Correct ?    6 Yes 10 No

a)If column dimensions are 250*400mm , what will be cutting length for 8mm stirrups and how to ca..

Answer / ram bhawan

2(A+B)+16*DIA OF STIRRUP BAR

A = INNER HEIGHT OF STIRRUP
B = INNER BREATH OF STIRRUPS

IF CLEAR COVER IS GIVEN (COVER GIVEN FROM STIRRUP NOT FROM
MAIN BAR)

Is This Answer Correct ?    2 Yes 9 No

a)If column dimensions are 250*400mm , what will be cutting length for 8mm stirrups and how to ca..

Answer / silpa

250-25+8=233mm,
400-25+8=383mm
2(0.233+0383)+16*0.08=2.512m

Is This Answer Correct ?    9 Yes 32 No

a)If column dimensions are 250*400mm , what will be cutting length for 8mm stirrups and how to ca..

Answer / anthony victor bernard

a)250-column cover both side+8*dia of rod
400-column cover both side+8*dia of rod
so cutting length is (.200+.350)*2+(2*5*.008)
=1.180 mts
(b)cutting length is (.150+.355)*2+(2*5*.008)
=1.090 mts
(c)cutting length is (.100+.350)*2+(2*5*.008)
=0.980 mts

Is This Answer Correct ?    11 Yes 38 No

a)If column dimensions are 250*400mm , what will be cutting length for 8mm stirrups and how to ca..

Answer / neelakantam

a)250-column cover both side+8*dia of rod
400-column cover both side+8*dia of rod
so cutting length is (.250+.400)*2-.160+.128
=1.268 mts
same as (b)

Is This Answer Correct ?    37 Yes 65 No

Post New Answer

More Civil Engineering Interview Questions

For raft 3000mm thickness with T25150 mesh reinf in top and bottom what diameter can be used for chair to support mesh reinforcement

4 Answers  


How to find out slope footing concrete

0 Answers   Ekta World, Punj Lloyd Ltd,


What is difference between combin footing & rapt footing

0 Answers  


What will be compressive strength of bricks , Hollow blocks, Solid blocks

14 Answers   Aimil, Daewoo, EIT, HCL, Logos, Pratibha Industries,


how much unit weight of an RCC Box 3.0mX3.0m will be of design mix concrete M30

1 Answers  






compression strength of first class brick should be

3 Answers  


In foundation design, while we do the base pressure check, we normally check if the attained pressure value is less than the GROSS BEARING CAPACITY of the soil which is the sum of net bearing capacity of soil and the overburden pressure. Actually, the overburden pressure acts against the net bearing capacity of the soil and I feel that we are actually increasing the bearing capacity value and doing the check. I feel that this is NOT right. Please clarify on this.

0 Answers  


Respected sir i am appearing for the exam this year.I will be highly obliged if u kindly send me last year's interview paper on civil engineering in my email address debosmitroy@yahoo.in

1 Answers  


In reclamation works what are the importance of geotextiles and sand?

0 Answers  


What are the precautions needs during concrete pouring in very hot weather?

1 Answers  


How to find weight of 1cu.m concrete in varies grades? and giive calculation.

2 Answers  


mix design procedure for 1:6 cement mortar

0 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)