How to calculate the individuals quantities of cement,sand,and aggregate
having 1:2:4 ratio for 50 cubic meter area.
Answer / palguna
The proportions of
cement-1 ,sand -2 aggregate-4, the sum of total aggregates is 7
the volume of wet cement concrete is 1.54 to 1.57
then the solution is cement = 1x1.57x1440/7= 322.57 kg
(here 1440 is density of cement
for sand = 2x1.57/7=0.4485 cum
aggregate = 4x1.57/7=0.897 cums
| Is This Answer Correct ? | 8 Yes | 4 No |
whch is the grade of OPC
what is void ratio??
What is water/cement ratio? Importance in construction?
Can anyone give me the thumb rule for calculating the time required for construction based on quantity of concrete, Reinforcement, shuttering, etc
the coefficient of curvature for a well graded soil must be inthe guage 0.5-1 3-4 4-5 none
how much steel used in 100 sq feet
For raft 3000mm thickness with T25150 mesh reinf in top and bottom what diameter can be used for chair to support mesh reinforcement
Why silt content not allowed more than 6% for Sand ?
time and work questions
what is mixed design, define it? what is way beecher?
How much quantity of Cement and Sand required for Cement Sand Ratio of 1:1 and volume of pile is 0.61 m3
Why is the statue of liberty made of copper?
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)