a)If column dimensions are 250*400mm , what will be
cutting length for 8mm stirrups and how to calculate it? b)
If beam dimensions are 200*400mm , beam coveris 25mm , slab
cover is 20mm , what will be the cutting length for
stirrups? c)Column dimensions are 250*400mm , reinf. is
12nos. bar of 16mm dia , stirrups provided are two legged,
what will be the length of each ring?
Regards
Answer Posted / er shailesh kr srivastava
A)CUTTING LENGTH FOR 8mm Strips=2(250+400-2*80-2*8+24*8)
2(650-160+22*8)
2(490+176)
=1332mm
same as for beam
| Is This Answer Correct ? | 6 Yes | 9 No |
Post New Answer View All Answers
what is the max. area can we apply the plate load test ?
why +1 to be followed for calculating the no of bars in BBS. Please explain
How to calculate woden area in sft and Cft
What happens when,in Prestressed girder the HDPE duct and cone size is provided more than required? (technical answer expected)
How high should the water tank be to provide a 60 psi at base of this water tower?
Thumb rule for steel qty for 1m2 in kg/m2 column slab footing beam
how to find quantity of concrete in PCC M15
What is kn measurement?
5. Do you feel that your present employer estimates your full work potential? Are they pleased with your work performance?
what energized you to complete your course?
how much of quantity of material required for execution of one cubic meter of random rubble masonry in 1:3 cement mortar
Scaffolding IS code NO.
I am a civil engineer . I am also selected for sbi clerk interview which is to be held on 4th May2010 is there anybody resembling the same? what question can be asked and what should be the probable answers?
relation bet Coefficient consolidation Cv, time factor Tv, drainage path d, & time t is Cv=d2Tv/t Cv=d2t/Tv Cv=tTv/d2 Cv=Tv/td2
what is the coefficient for running feet to cft coversion both area and price