Answer / umesh
slab length x breath x width = ans m3
L X B X W SIMPLE FORMULA TO FIND OUT THE QUANTITY OF CONCRETE
Is This Answer Correct ? | 44 Yes | 2 No |
Answer / rajendra
As per IS:456-2000 code of ractice in Cu.m.&
in simple formula as follows:
Length(m)X Breadth/Width(m)X Height/Depth(m)=ans Cu.m
Is This Answer Correct ? | 27 Yes | 2 No |
Answer / ashok subrahmanya
As per the drawings of cast insitu concrete(depending upon
weather its PT slab or rcc slab) we have 2 calculate the
pour area say A1.Now
Quantity of concrete per pour=
(A1*slab depth)+(Drop panel area*Extra depth of drop panel)+
(No of beams*Its c/s area*extra depth)
Is This Answer Correct ? | 22 Yes | 6 No |
Answer / jhulzkee
Calculate the volume of the structure to be poured by its
given dimensions on plan.
Is This Answer Correct ? | 5 Yes | 0 No |
Answer / suresh
QUANTITY OF CONCRETE=LENGTH OF STRUCTURE*WIDTH OF
STRUCTURE*THICKNESS OR DEPTH OF STRUCTURE
L*B*D=VOLUME
Is This Answer Correct ? | 2 Yes | 0 No |
Answer / peer mohamed anzar.s
There is no confusion (for example Take slab lenth ,bredth,width 1m*1m*0.1m Then answer will be =0.1cubic meter)
Is This Answer Correct ? | 1 Yes | 0 No |
Answer / shahnawaz
simply find out the volume of concreting area i;e LXBXH
orD=we will get the volume say cum (m3)
Is This Answer Correct ? | 1 Yes | 0 No |
Answer / akbar_u2u
total volume=length x breath x width
suppose
total volume=20'x 10'x .33'
total volume=66cft
Is This Answer Correct ? | 1 Yes | 1 No |
Answer / zuhair shamsedeen
by checking from structure drawing and arch - drawing
Is This Answer Correct ? | 2 Yes | 4 No |
please what are the required bars for a beams of 6mx6m and 450x300mm, one is continuous and the the second is discontinuous ..Its a commercial building (church)
purpose of binding wire in RCC. Structually is there any requirements that how to tie the binding wire like cross or single or how many pices combine together to bind the steel. i need structually importance of binding wire.
factory shed foundation l=4, b=3' d=8' rcc foudation for top to bottom pl tell me cement ,steel ,sand ,labour cost ,excavtion,soil is weak not so hard
Power grids in two adjacent states(A&B) are interconnected. Can power grid in state A can be represented by Thevenin Equivalent Circuit. If not explain Why?
to achieve the strength upto m-65 concrete what we should add a)more cement b)silica fume c)marecement with fly ash d)flyash
What is the difference between Hinged and pinned in Column ends
lap lenth
can any1 mail me IS CODES and quality check sheet of materials..? its urgent plz
On concrete surface 1sq.ft area hacking no's of hack?
B.M DIAGRAMS & S.F DIAGRAMS OF CONTINOUS BEAMS
For M25 concrete ,what is the maximum compressive strength at 28 days ?
6 Answers L&T, Techno Builders,
How Calculate Lap Length