what is schedule variance and give the formula

Answers were Sorted based on User's Feedback



what is schedule variance and give the formula..

Answer / varun

percentage of time taken to complete the task

schedule variance== (actual duration-planned
duration)/planned duration * 100


as per my knowledge this is answer

Is This Answer Correct ?    97 Yes 50 No

what is schedule variance and give the formula..

Answer / ravi

Schedule Variance= Earned Vlaue - Planned Value
Earned Value-> Budget value of the work completed in
specified time
Planned Value -> Budget value of the work that was planned
to be completed in specific time
The difference reflects the amount of budget that could not
be completed or that was excessively done in specific time.

Is This Answer Correct ?    49 Yes 13 No

what is schedule variance and give the formula..

Answer / kt karthikeyan

Schedule Variance = (Actual Completion Date – Planned
Completion Date)/(Planned Completion date – Planned Start
Date + 1) * 100

Is This Answer Correct ?    57 Yes 27 No

what is schedule variance and give the formula..

Answer / hannah

SV = [(Actual End Date - Planned End Date)/(Planned End
Date - Planned start Date)]*100

Is This Answer Correct ?    31 Yes 12 No

what is schedule variance and give the formula..

Answer / manju

Scheule Variance = [(Actual Calendar Days - Planned
Calendar Days)/Planned Calendar Days]*100

Is This Answer Correct ?    16 Yes 12 No

what is schedule variance and give the formula..

Answer / tamil

Schedule Variance.

First find out the Delay(AED(Actual END Date)-PED(Planned
END Date)). Formula for this:

=IF(Actual Finish date="",0,IF(Actual Finish Date = Planned
Finish Date,0,IF(Actual Finish Date>Planned Finish
Date,NETWORKDAYS(Actual Finish,Planned Finish)-1,NETWORKDAYS
(Actual Finish,Planned Finish))))).

And then Find out the Actual Schedule(PED(Planned End Date)-
PSD(Planned Start Date)). Formula for this:
NETWORKDAYS(Planned Finish date,Planned Start Date)

And then Finally Schedule Variance Formula Is:

IF(NOT(Actual Schedule=0),(Actual Schedule/Delay%),0)

Please check it....

Is This Answer Correct ?    7 Yes 3 No

what is schedule variance and give the formula..

Answer / manas

There is difference between schedule variance and schedule slippage.
Schedule slippage- Schedule slippage is key performance indicator that shows amount of time the project is delayed (expressed in %) compared to its baseline start and Finish dates.
Formula for computation of schedule slippage: - (Actual Project Duration – Planned Project Duration / Planned Project Duration) * 100
Formula for compute Actual Project Duration: - (Project Actual End Date – Project Actual Start Date)
Formula for compute Planned Project Duration or baseline duration: - (Project Planned End Date – Project Planned Start Date)

Schedule Slippage metrics helps in identifying the problems of previous projects and making more realistic predictions for future projects

Schedule Variance- 
Schedule Variance term is used in EVM which states how much cost of work is yet to be completed as per schedule.
SV- BCWP-BCWS.

Is This Answer Correct ?    3 Yes 0 No

what is schedule variance and give the formula..

Answer / harsh

These answers looks unrealistic. If we want to calculate SV
and EV during the project, how it can be calculated then.

SAP uses concept of POC (Percentage of completion)to
calculate EV & SV

SV - (Scheduled Effort - Burnt Effort)/ Scheduled Effort

Definition -
Scheduled Efforts (BCWS) = Estimated POC * Estimated Effort
Burnt efforts(BCWP)= Actual POC X Estimated Effort
Estimated POC = (Current Date - Planned Start Date)/ Total
Planned Duration
Actual POC = (Total planned efforts for project - total
spent efforts(Present state))/ Total Planned efforts for
project.

Is This Answer Correct ?    2 Yes 0 No

what is schedule variance and give the formula..

Answer / g.vijayan(annamalai university

schedule variance=(actual duration-planned
duration)/planned duration*100

Is This Answer Correct ?    2 Yes 0 No

what is schedule variance and give the formula..

Answer / sushilkumar pandey

SV = (Actual-Estimated)*100/Estimated

If
Estimated Duration= 43 Days
Actual Duration = 45 Days

Then

SV = (45-43)*100/43

SV = 200/43

SV = 4.65

Is This Answer Correct ?    7 Yes 6 No

Post New Answer

More Manual Testing Interview Questions

How would you test a WINDOWS application...? & How you are going to test a WEB applicaiton...?

1 Answers   Broadridge,


what is the defference between stress and load testing?

5 Answers   TCS,


Can u test a website or a webapplication manually without using any automation tool?

4 Answers   IBM,


Hey guys, Developers compile the code they write. That is a kind of testing!! Which category it belongs to in Testing. Static testing or Dynamic testing. Please clarify

13 Answers   IBM,


Difference between Agile process and Water Fall model

0 Answers   Cap Gemini,






What is the difference between bug , error and defect ? Explain with example. 2... What is diff between test approach , test strategy, Test plan and test methodology documents? 3...How to test a website with manual testing? 4. What methodologies have you used to develop test cases?

13 Answers   Infosys, SCI, Wipro,


Hai, Iam Venu completed BCA with MBA in May 2007. Now iam learning Manual Testing .So plz help me if you find any Interview or if you find any software trainee chance in testing ?9347727155

1 Answers  


How will you prepare traceability matrix if there is no Business Doc and Functional Doc?

0 Answers   Infosys, Notion Ink,


What r the different types of testcase techniques?

15 Answers  


Yester Day i Attended a interview interviewer asked that Due to Sum Bug the total Testing process is Blocked and still hundred test cases are remaining to execute with in a week u have to reliese to the customer at that time what will you do?

6 Answers   NSN,


What is the first query u encounter to test a database..?

2 Answers   IBM,


why we need quality assurance?

1 Answers  


Categories