Answer Posted / sushilkumar pandey
SV = (Actual-Estimated)*100/Estimated
If
Estimated Duration= 43 Days
Actual Duration = 45 Days
Then
SV = (45-43)*100/43
SV = 200/43
SV = 4.65
| Is This Answer Correct ? | 7 Yes | 6 No |
Post New Answer View All Answers
Can you explain boundary value analysis?
What is a test scenario?
In manual testing, what are stubs and drivers?
Which are the standards for software test plans?
What is a test log?
what are the responsibilities for QA tester to test application on UNIX environment??? what skills required for unix???
What is an error?
negative test cases on banking domain ?
What does entry and exit criteria mean in a project?
what is the difference between PEGA based web application testing versus web application testing?
What is testing and maintenance?
what is prototyping model,RAD model V model, spiral model?????
KINDLY FORWARD ME THE INTERVIEW QUESTIONS & ANSWERS FROM REAL TIME POINT OF VIEW FOR 1.5 YEARS EXPERIENCED CANDIDATE. MY EMAIL ID IS sky_bird433@yahoo.com
How to do manual testing of a E-insurance project (end to end process)
Could someone please send me real check list for Database Security testing.Please my mail ID- patil.ramchandra@yahoo.co.in. Thanks.