what is schedule variance and give the formula

Answer Posted / sushilkumar pandey

SV = (Actual-Estimated)*100/Estimated

If
Estimated Duration= 43 Days
Actual Duration = 45 Days

Then

SV = (45-43)*100/43

SV = 200/43

SV = 4.65

Is This Answer Correct ?    7 Yes 6 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What r the functional testing u perform?

1652


What is Traditional testing & Object Oriented testing?

1965


In Quality Center, If we can reuse a non reusable test script as template test, then what is the need of defining reusable test scripts? What additional functionality does Reusable test scripts add when compared to non reusable test scripts?

2560


What are the bussiness scenories?

2644


define risk management system with example ?

1562






what are the various techniques you will use as soon as the srs was given to you to speedup the testing?

1543


what are the possible test cases for online jobs search portal..if its a job seeker module and any 1 if u had worked on this proj pls share the bugs with sev and priority pls frends i need replies for these queries ..thanks in advance

7139


Explain the defect life cycle.

627


what are the tests u did in entire project? when it did in the project? (means at the release build to end of project) plz explain clearly

1658


What exactly is quality control?

728


Can test condition,testcase and testscript help u in performing the static testing

1611


What is Dynamic Binding and Dynamic Loss?

1590


how will you estimate of your website?

1668


hi experts, i was asked to write down the requirement description,test scenario, and test cases for gmail login and send email and then to check the email was sent in the sent mails.the format given to me was like this: Req ID, Req description, Test Scenario, Test cases....Can anybody please help me out with this..

1583


Have you prepared traceability matrix and how to prepare it?

1599