Answer Posted / sushilkumar pandey
SV = (Actual-Estimated)*100/Estimated
If
Estimated Duration= 43 Days
Actual Duration = 45 Days
Then
SV = (45-43)*100/43
SV = 200/43
SV = 4.65
| Is This Answer Correct ? | 7 Yes | 6 No |
Post New Answer View All Answers
Give me an example of something you tried at work but did not work out so you had to go at things another way.
What is stub?
I have an Interview about Guidewire claimcenter,so could you provide any info regd it?.I would really appreciate any kind of help- email at hvshah2001@gmail.com
any one please send me any test case examples with tabular columns in manual testing
What is Batch testing? Facets Benefit Configuration
1.what promted you to become involved in QA/Testing?
why use caffine for HPLC calibration ?
how deployment phase of SDLC differs in product based and in service based company ?
What is the big deal about ‘requirements’?
what is test case management?explain in brief.
What makes a good software qa engineer?
You must test a trouble report where the problem cannot be reproduced. You tried using various test data files and mutations from the data files the customer sent along with the trouble report. The software does not fail the way it did at the customer's site.
Why Equivalence Partitioning is called equivalence or what is the significance of equivalence term in ECP?
Hi Friends, Can anubody give me brief overview of Automation tools.. (basics of tools-summary)of following tools? 1.Qualty Center 2.Load Runner 3.Win Runner 4.Q.T.P mail me on ...rachna.huda@gmail.com
which test strategy your are fallowing in your company?which documents u r using in software development life cycle?