Answer Posted / sushilkumar pandey
SV = (Actual-Estimated)*100/Estimated
If
Estimated Duration= 43 Days
Actual Duration = 45 Days
Then
SV = (45-43)*100/43
SV = 200/43
SV = 4.65
Is This Answer Correct ? | 7 Yes | 6 No |
Post New Answer View All Answers
What r the functional testing u perform?
What is Traditional testing & Object Oriented testing?
In Quality Center, If we can reuse a non reusable test script as template test, then what is the need of defining reusable test scripts? What additional functionality does Reusable test scripts add when compared to non reusable test scripts?
What are the bussiness scenories?
define risk management system with example ?
what are the various techniques you will use as soon as the srs was given to you to speedup the testing?
what are the possible test cases for online jobs search portal..if its a job seeker module and any 1 if u had worked on this proj pls share the bugs with sev and priority pls frends i need replies for these queries ..thanks in advance
Explain the defect life cycle.
what are the tests u did in entire project? when it did in the project? (means at the release build to end of project) plz explain clearly
What exactly is quality control?
Can test condition,testcase and testscript help u in performing the static testing
What is Dynamic Binding and Dynamic Loss?
how will you estimate of your website?
hi experts, i was asked to write down the requirement description,test scenario, and test cases for gmail login and send email and then to check the email was sent in the sent mails.the format given to me was like this: Req ID, Req description, Test Scenario, Test cases....Can anybody please help me out with this..
Have you prepared traceability matrix and how to prepare it?