Answer Posted / harsh
These answers looks unrealistic. If we want to calculate SV
and EV during the project, how it can be calculated then.
SAP uses concept of POC (Percentage of completion)to
calculate EV & SV
SV - (Scheduled Effort - Burnt Effort)/ Scheduled Effort
Definition -
Scheduled Efforts (BCWS) = Estimated POC * Estimated Effort
Burnt efforts(BCWP)= Actual POC X Estimated Effort
Estimated POC = (Current Date - Planned Start Date)/ Total
Planned Duration
Actual POC = (Total planned efforts for project - total
spent efforts(Present state))/ Total Planned efforts for
project.
Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
What is bug severity?
how recovery manager works in winrunner
aplitue questions will be based on wich type ?
which test strategy your are fallowing in your company?which documents u r using in software development life cycle?
What are the different strategies for rollout to end users?
Can you explain boundary value analysis?
Negative test cases for phone camera
Assume a login page, and you have written 10 cases(say for example). How will you justify that these 10 testcase suffient for the login and how do you say this is 100% satisfies the need.
how to indentify memory leakages after the build
Hi, I was asked following question during a interview. Please answer it: Password field is there,we can accepts every character except underscore and semicolon. It can accept min 6 characters and maximum 12 characters. Prepare boundary value and equivalence class test cases.
When should you opt for manual testing over automation testing?
How do you go about testing a project?
What is ofx testing?
can any one send sample test cases for database testing by taking an example? also leave emailid please. thanks (very urgent)
IN SQL SERVER 2005, With out using Query, hw can u break down USER NAME & PASSWORD to enter the software.