Answer Posted / ravi
Schedule Variance= Earned Vlaue - Planned Value
Earned Value-> Budget value of the work completed in
specified time
Planned Value -> Budget value of the work that was planned
to be completed in specific time
The difference reflects the amount of budget that could not
be completed or that was excessively done in specific time.
Is This Answer Correct ? | 49 Yes | 13 No |
Post New Answer View All Answers
What does you mean by positive and negative testing & what is the difference between them. Can anyone explain with an example?
value momentum
When have you had to focus on data integrity?
what is the difference between Desktop testing,Client/server testing and webapplication testing
what are the risks and contingencies u had in ur project?
How to do manual testing of a E-insurance project (end to end process)
What is back to back testing?
Explain branch coverage and decision coverage.
Test cases have written according to Flow of the software working or according to Screens?
What r the things,u prefer and prepare before starting testing?
What is the difference between manual testing and automation testing?
I have 2 years of exp. in testing and looking for a change if any body knows, about any vacancy in testing then plz contact me on deepti_ac@yahoo.co.in
How do you define a testing policy?
How do u determine,what to be tested?
Can you explain process areas in cmmi?