Answer Posted / varun
percentage of time taken to complete the task
schedule variance== (actual duration-planned
duration)/planned duration * 100
as per my knowledge this is answer
Is This Answer Correct ? | 97 Yes | 50 No |
Post New Answer View All Answers
What is state transition?
can any one post the format of tracebility martrix Plz...... Maid Id: sandhya.shyamala@yahoo.com
hi this is chik here iam showing my current project ERP and am prepair in hr model please tell me details about it and what all function test in hr model and give me some test caserelated to this module.Please tell me am faceing lots of problem in interview am not able to explain in interview please help me out my id is chiku_69@yahoo.in
What do you plan to become after say 2-5yrs (Ex: QA Manager, Why?)
Suggest some book to learn more test case???
If date field is a text field write test cases to validate it?
What is the test harness?
In which all places, testing is done?One is from the server by calling server name.Can u suggest others?
what are the 3 test tool categories and describe what each can do.
What are the different levels of manual testing?
Name three reasons why the tester may choose to record in Context Sensitive mode.
i need manual testing interview questions for 2+ experience plzz help me..
How the application is launched to the production environment?
What is Independent Testing?
can we do database testing in manual testing? then how we write the test case?