Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


Yester Day i Attended a interview interviewer asked that
Due to Sum Bug the total Testing process is Blocked and
still hundred test cases are remaining to execute with in a
week u have to reliese to the customer at that time what
will you do?

Answers were Sorted based on User's Feedback



Yester Day i Attended a interview interviewer asked that Due to Sum Bug the total Testing process ..

Answer / a sameer

Analyse the question, from the question we got the below points

1. Its blocking the application to move forward ( showstopper).
2. There is client release in due next week.
3. Hundred's of test cases remained to execute.

From the above things we can do the follow actions

1. Try to resolve the bugs ASAP and meanwhile execute those
test cases which are not related to those scenario. In this
way we can have sufficient time to test the bugs and at the
same time we can check the bugs regression.

2. Extend the client day explaining the severity of the bugs.

3. If the bugs is too hard to solve within the timestamp
available the best option left would be revert back the
previous latest version we had ( if it is jut few weeks back
release) and try to fix the new enhancement quickly.

Is This Answer Correct ?    10 Yes 0 No

Yester Day i Attended a interview interviewer asked that Due to Sum Bug the total Testing process ..

Answer / remo

It is clear from the question we cannot proceed with
testing unless and until the bug is fixed. So next step
should be resolving the bug. if the bug is not critical,
then fix the bug and proceed further with testing , if it
critical and if it needs some time to be fixed, we have to
extend the dead lines(Delivery to the customer.)

If it is an onsite project we will send mail to the client
and will setup a client Call. In the client call the same
is discussed with the client and depending on the client
response we will take the necessary actions.

Is This Answer Correct ?    10 Yes 2 No

Yester Day i Attended a interview interviewer asked that Due to Sum Bug the total Testing process ..

Answer / chennamsubbaraidu

U suppose 2 say that
1. First i will Execute high severity bugs
2. check the basic and main functionality test cases
for every module u suppose 2 have the main functionality
test cases and high severity test cases.
3.then u suppose 2 give the preference to show stopper
errors test cases.By watching the flow of the module u can
undersatnd.

Is This Answer Correct ?    5 Yes 0 No

Yester Day i Attended a interview interviewer asked that Due to Sum Bug the total Testing process ..

Answer / kiran

Question clearly says that due to show stopper(Bug) Testing
cannot be continued and yet to execute hundred of test
cases in a weeks time.

1. Analyse the bug and inform the development to fix ASAP.
See the feasbility how much time required to fix it.
2. Extend the client delivery day by explaining the
severity and complexity of Bug.
3. You need to discuss with u r manager or clients for
choosing alternate environment to meet deadlines(If
application has parallel environments)
4.If not u need to record schedule slipage for Management
activities.
5.Once u r issue is resolved, you need to pick high
priority test cases(Business specified scenarios) and
execute them to avoid schedule slippage expect to be
delivered to client.

Hope this answer might be useful for all.

Thanks

Is This Answer Correct ?    2 Yes 0 No

Yester Day i Attended a interview interviewer asked that Due to Sum Bug the total Testing process ..

Answer / santhi

What did you answered?

Is This Answer Correct ?    2 Yes 2 No

Yester Day i Attended a interview interviewer asked that Due to Sum Bug the total Testing process ..

Answer / sreenivas

I Said i will follow Root cause analysis,and rollback, work
for more hours on the problem and i will resolve the
problem like that i said. tell me your answers
pls
Post to
seenu.jawaji@gmail.com

Is This Answer Correct ?    0 Yes 3 No

Post New Answer

More Manual Testing Interview Questions

what is security testing? can u please set an example for it?

5 Answers  


explain bug cycle

10 Answers   Cap Gemini,


What are the main key components in web applications?

0 Answers  


Which criteria should take in account while doing CMS testing of any project?

0 Answers  


First Name & Last Name fields are there in the application form, In Application First name & last name fields accepts the numerical value 453455 & special characters $%#$% . My question is that --> I think No need to write test cases for Numerical value & special char. for First & Last name fields BECAUSE No one will enter such a input data at client side b'coz it's not practical. Let's me know the answer.

3 Answers  


What is bug priority?

0 Answers  


Whether we write one test case for one use case?

3 Answers  


Explain Boundary value analysis, Equivalence partitoning and Error guessing?

1 Answers   IBM,


what is Entrance and Exit criteria ?

2 Answers   HCL,


Which type of testing combines two modules?

6 Answers   ABC, Business One,


What actually testers do in Smoke Testing?

18 Answers   Patni,


difference between web based server and client based server?

2 Answers  


Categories