Onsite percentage wastage of Concrete, Rebar, Blockwork/Brickwork, Plaster, Floor tiles ??
Answers were Sorted based on User's Feedback
Answer / sjtbehera
concrete wastage can be taken in to individual i.e
sand-5%. aggregate-5%, rebar-2.5% up to 16mm than 5% above
cement wastage can be taken 5%,
brickwork- 7% can be taken. plaster and floor tiles can be
taken -2.5% of all material.
| Is This Answer Correct ? | 7 Yes | 2 No |
Answer / karthik rajendren
3% for Concrete & rebar
5% for Brick/Block Work,Plaster& Tile
| Is This Answer Correct ? | 3 Yes | 0 No |
what does a civil engineer should know?
why development length = 50D . why not 100D
how to take out quantity of steel used in column and beam?? what is standard formula for it???
what is the mix design for M45 concrete
What is plasticiser and where it will use?
clean earthing and dirty earthing
1 Answers CSCEC-China State Construction Engineering Corporation,
How much cost is required for 1 Flyash Brick?
Tell me about triple point of water.
Define graphics window?
sir please send me campus placement questions in civil engineering
Method of findingthe dry ingredient quantity of 1 m3 concrete.
25 Answers Annai Infra Developers, GKC Projects Limited GKCPL, IRE, L&T, Mahle Filter Systems, NCC, PNRD, Rama, RCC, Shivani Agriculture, Sobha Developers, Suraj Constructions, TCL,
How reactor of SBR installed , is it be over ground, fully under ground or semi sunk ?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)