Onsite percentage wastage of Concrete, Rebar, Blockwork/Brickwork, Plaster, Floor tiles ??
Answers were Sorted based on User's Feedback
Answer / sjtbehera
concrete wastage can be taken in to individual i.e
sand-5%. aggregate-5%, rebar-2.5% up to 16mm than 5% above
cement wastage can be taken 5%,
brickwork- 7% can be taken. plaster and floor tiles can be
taken -2.5% of all material.
Is This Answer Correct ? | 7 Yes | 2 No |
Answer / karthik rajendren
3% for Concrete & rebar
5% for Brick/Block Work,Plaster& Tile
Is This Answer Correct ? | 3 Yes | 0 No |
what is the compressive strenth of m30 grade cocrete column at 7 days
How to calculate density(dry & bulk) of sand from Sp. ravity value of sand. eg. G=2.5
What is the ratio of materials used for M10, M15, M20 & M25 grades of concrete? Also specify the quantity of water used in each grade & how to calculate it?
silt maximum in sand.
what is called super elevation of the road?
How to do BBS for Chair Rod?
If we use oil,inner on the column box, it'll make rust on the column steel?
what is the density of concrete & steel? where we are using pycnometer? what is bulking of sand? what is under reinforced & over reinforced? what is balanced section?
what are the types of design? which type of method is used at what type of design & why?
How much 1 cum of M15, M20 & M25 concrete weigh?
In which direction is bottom bar of rectangular footing is placed in short or long.
what is the difference in density of fresh concrete and hardened concrete?
1 Answers GPSC Gujarat Public Service Commission,