how much quantity are required like cement,sand,aggregate
for (46*29*0.41)feet slab? how much this quantity can be
calculated?
Answers were Sorted based on User's Feedback
Answer / asad ali
wet volume conc: = 546.94 cu.ft
lets supposed ratio of conc: = (1:2:4)
sum of ratio = 7
first we find dry volume according to nature
dry volume of con: = 546.94*1.54 = 842.287cu.ft
1.54 is constant for conc: and 1.27 is constant for mortar
after a that we find cement,sanda and crush quantity OK
quantity of cement = ratio of cement *dry volume
--------------------------------
sum of ratio
this is the formula OK
= 1*842.287/7
=120.32 cu.ft OK
in bags of cement
we know that one bag of cement = 1.25cu.ft
so there fore 120.32/1.25 = 96.26 bags
say 96.5 bags
quantity of sand = ratio of sand * dry volume / sum of ratio
= 2*842.287 = 240.65cu.ft
quantity of crush = ratio*dry volume / sum of ratio
= 4*842.287/7
= 481.306cu.ft OK
quantity of cement = 96.5 bags
quantity of sand = 240.65 cu.ft
and last one
quantity of crush = 481.306 cu.ft
OK OK Ok Ok Ok any Question about contact me
civil.com7875@yahoo.com
Is This Answer Correct ? | 12 Yes | 0 No |
Answer / jaydeep
total area 546.94 cubicfeet = 15.60 cubic meter
now for aggregate = 15.60 x 0.9 = 14.04 cubicmeter
for cement = 15.60 x 6.25 = 97.5 bags
the ratio of cement, sand and aggregate is 1:2:4 needed
Is This Answer Correct ? | 1 Yes | 1 No |
how much deduction will be in 32 mm dia HYSD steel bar for 45 and 90 degree bend
0 Answers CDSIPL Centrodorstroy India Pvt Ltd,
how much binding wire is required for one tone steel
20 Answers Gammon, Hinduja, Jindal,
how to Concrete cubes testing curing time 7 days casting date 24.05.17 testing date ?
Pile height is 4.3m. 2nos. under reammer. bulb nose is 75mm and height is 400mm. pile dia is 375mm and overall dia 940mm.pls. help to calculate concrete in pile and bulbs separately. What is formula for bulb volume calculation ?
1) what is the difference between development length & overlap length ? 2) why extras are provided at top and bootom in a beam of slab? 3) why stirrups are provided at 0.3l at supports and 0.4l at center? 4) is column a compression memeber if yes how & beam is which type of memeber?
Why we are using 150 mm X 150 mm X 150 mm cubes for testing the compressive strength of concrete in CTM and why not other sizes?
200mm*200mm thick block work 1sqm how many cement bags
For plate load test why we are applying pressure 3 times the proposed allowable bearing pressure? Is there any supporting standards for this?
How to calculate steel for beam slab and column
Providing cement based water proofing treatment to terrace (Indian water proofing) with brick bats with cement morter (1:5) and (1:3). what are rate in cum or sqm.
Why did you choose to communicate with our organization ?
Brick is fire resistant than stone because––