Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


how much quantity are required like cement,sand,aggregate
for (46*29*0.41)feet slab? how much this quantity can be
calculated?

Answers were Sorted based on User's Feedback



how much quantity are required like cement,sand,aggregate for (46*29*0.41)feet slab? how much this..

Answer / asad ali

wet volume conc: = 546.94 cu.ft
lets supposed ratio of conc: = (1:2:4)
sum of ratio = 7
first we find dry volume according to nature
dry volume of con: = 546.94*1.54 = 842.287cu.ft
1.54 is constant for conc: and 1.27 is constant for mortar
after a that we find cement,sanda and crush quantity OK
quantity of cement = ratio of cement *dry volume
--------------------------------
sum of ratio
this is the formula OK
= 1*842.287/7
=120.32 cu.ft OK
in bags of cement
we know that one bag of cement = 1.25cu.ft
so there fore 120.32/1.25 = 96.26 bags
say 96.5 bags
quantity of sand = ratio of sand * dry volume / sum of ratio
= 2*842.287 = 240.65cu.ft
quantity of crush = ratio*dry volume / sum of ratio
= 4*842.287/7
= 481.306cu.ft OK
quantity of cement = 96.5 bags
quantity of sand = 240.65 cu.ft
and last one
quantity of crush = 481.306 cu.ft
OK OK Ok Ok Ok any Question about contact me
civil.com7875@yahoo.com

Is This Answer Correct ?    12 Yes 0 No

how much quantity are required like cement,sand,aggregate for (46*29*0.41)feet slab? how much this..

Answer / jaydeep

total area 546.94 cubicfeet = 15.60 cubic meter

now for aggregate = 15.60 x 0.9 = 14.04 cubicmeter

for cement = 15.60 x 6.25 = 97.5 bags

the ratio of cement, sand and aggregate is 1:2:4 needed

Is This Answer Correct ?    1 Yes 1 No

how much quantity are required like cement,sand,aggregate for (46*29*0.41)feet slab? how much this..

Answer / salim_rambo

546

Is This Answer Correct ?    0 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

material cost to cast m20 grade rcc

1 Answers   CCCL,


Why we are using coarse sand for brick work and is there any technical problem if, we use fine sand instead of coarse sand.

4 Answers  


What is the cement and sand content in the mortar used to build 1 sqm of 190x190x390mm hollow and solid blockworks?

2 Answers  


you are planning to paint a newly fabricated workshop building made of structural steel of 10 tons total mass.you are require to paint 1 cot of primer and 2 coats of top coat.How many liters of primer and top coat you will request

2 Answers  


Differenciate between One way slab and two way slab

5 Answers  


five benefits of using standard terminology in the measurement process

0 Answers  


In how many types u can do POP on ceiling and walls(on which material or by using which material)? b) what is the difference between dry , oil bound, enamel, acrlyic type of painting? 2nd :- I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?

0 Answers  


How to calculate concrete in percentage wise ,for example cement 18% sand 40% aggregate 40% and Stell 2% ,I need and??

0 Answers  


Hello sir,I am preparing for GET,Jindal steel & power limited.So can u plz send me few back papers including technical & aptitude.

2 Answers   Jindal,


how to take the quantity of block work and plastering  1block price:3saudi riyal cement:1bag:15 saudi riyal sand:3bag:20 saudi riyal 1mason:9hour per hour 40 saudi riyal 1labour:9hour per hour 40 saudi riyal can anybdy calculate

0 Answers  


How to calculate Volume of Wet cement concrete for a specific grade?

0 Answers   MBPL,


What is the size of a standard room?

1 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4453)
  • Electrical Engineering Interview Questions Electrical Engineering (16638)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)