how much quantity are required like cement,sand,aggregate
for (46*29*0.41)feet slab? how much this quantity can be
calculated?
Answers were Sorted based on User's Feedback
Answer / asad ali
wet volume conc: = 546.94 cu.ft
lets supposed ratio of conc: = (1:2:4)
sum of ratio = 7
first we find dry volume according to nature
dry volume of con: = 546.94*1.54 = 842.287cu.ft
1.54 is constant for conc: and 1.27 is constant for mortar
after a that we find cement,sanda and crush quantity OK
quantity of cement = ratio of cement *dry volume
--------------------------------
sum of ratio
this is the formula OK
= 1*842.287/7
=120.32 cu.ft OK
in bags of cement
we know that one bag of cement = 1.25cu.ft
so there fore 120.32/1.25 = 96.26 bags
say 96.5 bags
quantity of sand = ratio of sand * dry volume / sum of ratio
= 2*842.287 = 240.65cu.ft
quantity of crush = ratio*dry volume / sum of ratio
= 4*842.287/7
= 481.306cu.ft OK
quantity of cement = 96.5 bags
quantity of sand = 240.65 cu.ft
and last one
quantity of crush = 481.306 cu.ft
OK OK Ok Ok Ok any Question about contact me
civil.com7875@yahoo.com
| Is This Answer Correct ? | 12 Yes | 0 No |
Answer / jaydeep
total area 546.94 cubicfeet = 15.60 cubic meter
now for aggregate = 15.60 x 0.9 = 14.04 cubicmeter
for cement = 15.60 x 6.25 = 97.5 bags
the ratio of cement, sand and aggregate is 1:2:4 needed
| Is This Answer Correct ? | 1 Yes | 1 No |
why building got air crack? if it get in one particular are what is means?
how many tonnes equals to one cubic feet?
What should be the maximum allowable time for placing ready mix concrete? The specification requires concrete placement within 90 minutes of batching at the plant. What is the significance of this 90 minutes & should this be used as a rejection criterion? What effects does the concrete has after that time period?
what is formula for concrete mix ratio in m20, m25 and m30?
2 Answers Reddy Veeranna Constructions,
Types of pipes?
What is the PH value for domestic water supply
What are the points to be considered for calculating cement reconciliation. a)Do we need to deduct the wt of cement bags b)Do we need to adjust the qty due to wt loss during transportation, loading unloading etc or else each bag can be considered as 50 kg bag c)What is the proportion of mix cover block making.
If we know the N - Value of soil and required bearing capacity how do we know what diameter and length of pile to be casted? How can we check whether the dia. and lenght of pile we have selected are most economical onse?
what is meant by skyscapers?
A sieve analysis results in 100% retained in no. 50 Sieve, the fm is?
cement quantity in 1 M3 pcc
what is the density of steel and concrete in kg/m3?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)