Answer / asad ali
wet volume conc: = 546.94 cu.ft
lets supposed ratio of conc: = (1:2:4)
sum of ratio = 7
first we find dry volume according to nature
dry volume of con: = 546.94*1.54 = 842.287cu.ft
1.54 is constant for conc: and 1.27 is constant for mortar
after a that we find cement,sanda and crush quantity OK
quantity of cement = ratio of cement *dry volume
--------------------------------
sum of ratio
this is the formula OK
= 1*842.287/7
=120.32 cu.ft OK
in bags of cement
we know that one bag of cement = 1.25cu.ft
so there fore 120.32/1.25 = 96.26 bags
say 96.5 bags
quantity of sand = ratio of sand * dry volume / sum of ratio
= 2*842.287 = 240.65cu.ft
quantity of crush = ratio*dry volume / sum of ratio
= 4*842.287/7
= 481.306cu.ft OK
quantity of cement = 96.5 bags
quantity of sand = 240.65 cu.ft
and last one
quantity of crush = 481.306 cu.ft
OK OK Ok Ok Ok any Question about contact me
civil.com7875@yahoo.com
| Is This Answer Correct ? | 12 Yes | 0 No |
Answer / jaydeep
total area 546.94 cubicfeet = 15.60 cubic meter
now for aggregate = 15.60 x 0.9 = 14.04 cubicmeter
for cement = 15.60 x 6.25 = 97.5 bags
the ratio of cement, sand and aggregate is 1:2:4 needed
| Is This Answer Correct ? | 1 Yes | 1 No |
material cost to cast m20 grade rcc
Why we are using coarse sand for brick work and is there any technical problem if, we use fine sand instead of coarse sand.
What is the cement and sand content in the mortar used to build 1 sqm of 190x190x390mm hollow and solid blockworks?
you are planning to paint a newly fabricated workshop building made of structural steel of 10 tons total mass.you are require to paint 1 cot of primer and 2 coats of top coat.How many liters of primer and top coat you will request
Differenciate between One way slab and two way slab
five benefits of using standard terminology in the measurement process
In how many types u can do POP on ceiling and walls(on which material or by using which material)? b) what is the difference between dry , oil bound, enamel, acrlyic type of painting? 2nd :- I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?
How to calculate concrete in percentage wise ,for example cement 18% sand 40% aggregate 40% and Stell 2% ,I need and??
Hello sir,I am preparing for GET,Jindal steel & power limited.So can u plz send me few back papers including technical & aptitude.
how to take the quantity of block work and plastering 1block price:3saudi riyal cement:1bag:15 saudi riyal sand:3bag:20 saudi riyal 1mason:9hour per hour 40 saudi riyal 1labour:9hour per hour 40 saudi riyal can anybdy calculate
How to calculate Volume of Wet cement concrete for a specific grade?
What is the size of a standard room?
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)