Onsite percentage wastage of Concrete, Rebar, Blockwork/Brickwork, Plaster, Floor tiles ??
Answer Posted / sjtbehera
concrete wastage can be taken in to individual i.e
sand-5%. aggregate-5%, rebar-2.5% up to 16mm than 5% above
cement wastage can be taken 5%,
brickwork- 7% can be taken. plaster and floor tiles can be
taken -2.5% of all material.
| Is This Answer Correct ? | 7 Yes | 2 No |
Post New Answer View All Answers
) Design a gussetted base for a column section consisting of one sc 250 with two cover plates 300 x 25 mm carrying an axial load of 2500 KN. The S.B.C. of soil is 250 KN/m2 and the permissible bearing pressure on concrete is 4000 KN.
What is soil enforcement?
How do you measure water flowing through 300mm diameter pipes?
What was asked in isro civil interview
types of laps in column
when it is noted "JAMB SIM" what is the term "SIM" and what does it mean?
what is spacing of wallar support of 3m column. the thickness of column is 0.25 m.
how do you calaculate the total steel quantity of an rcc building using thumb rule?
What is the quantity of cement used for stone pitching work of 100sqm 225mm thick and cement mortar of 1:6? And how?
What is the release of lien?
factory shed foundation l=4, b=3' d=8' rcc foudation for top to bottom pl tell me cement ,steel ,sand ,labour cost ,excavtion,soil is weak not so hard
in block masonry l=10',b=0.5',H=10',Calculate cement ,sand and no.Of blocks?
How much sand and cement requirement for 1 SQM 125mm thickness Brickwork
An interior designer designed a rack with the given dimensions. The dimensions are in feet. This coplanar frame repeats at every 5feet and constitute a space frame. The total length is 120feet. Which steel member will you suggest? A square bar, A square tube or a circular tube. Explain.
i am completed my b.tech EEE in 2009,,,iam trying the job 3+ for AUTO CAD (ELECTRICAL),, what is the market for autocad electrical in hyderabad... how to handle the intervws give some suggestions ?