how amny bricks of size 240 mm X 120 mm X70 mm are required in
100 cubic meter brickwork. How much cement is required at 10
mm masonry and at 4:1 sand cement ratio and how much cubic
meter of sand is required for the above work.
Answers were Sorted based on User's Feedback
Answer / vijayshankar
1 Brick = 0.24*0.12*0.070 = 0.002016 Cu.m
For 1Cu.m = 1/0.002016 = 496 Bricks
For 100 Cu.m = 100*496 = 49600 Bricks.
Cm ratio 1:4
Consider the thumb rule method 25% of Cement mortar
required for the brick work
=0.25*100= 25Cu.m of Cement mortar
That means 25 Cu.m of Sand is required
Is This Answer Correct ? | 3 Yes | 0 No |
Answer / shyam sundar mondal
10mm th. with morter brick size=.25x.13x.08=.0026cum
volume of one brick with morter =.0026 cum
No of bricks one cum brick work = 1/.0026=385 nos
volume of one brick without morter = .24X.12X.07=.002016 cum
volume of morter =.0026*385-.002016*385 cum =.000584*385 cum
=.22484 cum
Dry volume of morter =1.20x.22484 =.2698 cum
Cement required = .2698/5=.05396/.0347*50=78kg
sand required = .2698/5*4=.05396*4 = 0.2158 cum
Is This Answer Correct ? | 4 Yes | 4 No |
A bill was raised by contractor which read as follows 1.) Excavation in normal soil upto 1.5m - 250 cum 2.) Excavation in normal soil 1.5m to 3m - 240 cum 3.) Excavation in soft rock - 350 cum 4.) Excavation in hard rock - 250 cum 5.) Filling with available soil - 825 cum 6.) Filling with bought out soil - 1100 cum How can I verify the above quantities, especially for item no. 5 & 6? What checks are necessary before releasing the bill ?
How many bags of cement will be required for 45.5 M^3 Concrete with the ratio of 1 Cement+1 Crash+ 2 Sand+1 Gravel?
0 Answers First MicroFinance Bank FMFB,
PERT Chart
Is there any codal provision for the use of Micro Silica in concrete?
what is the measure of slump
How we decide the the load combinations for design of RCC structures?
What is horizon or horizontal mining?
What are the important hardware systems used for cad?
what is Bearing Capacity,How to determine it?
how do we calculate quantity of gypsum for 1m3? 1m3 = ?kg
How to calculate concrete,s cement, sand, metal on the bases of its ratio. For any volume of work please give me brief calculation
curing of concrete why 7day's,14day's 21day's 28days