how amny bricks of size 240 mm X 120 mm X70 mm are required in
100 cubic meter brickwork. How much cement is required at 10
mm masonry and at 4:1 sand cement ratio and how much cubic
meter of sand is required for the above work.
Answer Posted / vijayshankar
1 Brick = 0.24*0.12*0.070 = 0.002016 Cu.m
For 1Cu.m = 1/0.002016 = 496 Bricks
For 100 Cu.m = 100*496 = 49600 Bricks.
Cm ratio 1:4
Consider the thumb rule method 25% of Cement mortar
required for the brick work
=0.25*100= 25Cu.m of Cement mortar
That means 25 Cu.m of Sand is required
| Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
Thumb rule for steel qty for 1m2 in kg/m2 column slab footing beam
What is meaning of tlc
What are segregation and bleeding?
Which is the indian standard code of line out. ? How much tolerance fot 1 mt lenght? Its challenge....
What is the bowing depth after stressing of PSC Girder of various spans and various dia of strands?
How to calculate the quantity of ingredients of M20 grade concrete?
For Wet Mix Mecadam design what is Optimum moisture content
how to calculate mivan shuttering matrial
How can you produce desired alloys and discuss their applications in daily life.
Laying bitumen concrete 40mm thick using 0.1372 cum of 13.2 10mm metal ,0.2387 cum of 10 5mm metal...what did it means please explain me how much cum of 10 mm metal need?
what is the specific gravity of rubble in plum concert
Can someone please be curing period of the following according to IS codes Column beam slab brick masonry raft found. and also tell how many hours/day
How many mortar required for Brickwork of 1 Cu.m works??
what will be density of a cement bag if its weight and volume are 50kg and 1.25 cft respectively???????
List out the potential risk factors for workers on the construction site?