Answer / mishijoshi
Code of practise for plane nad reinforced concrete : IS 456-
2000.
Is This Answer Correct ? | 256 Yes | 23 No |
Answer / rajkumar
Code for M20 and 25 are IS 456-2000 for concrete mix design
and element design and also IS-516 will be required for
testing of concrete.
Is This Answer Correct ? | 157 Yes | 38 No |
Answer / joseph ravi kiran
THE IS CODE FOR M20 & M25 IS ...IS 456:2000.
THIS CODE GIVES THE PROCEDURE OF MIX DESIGN.
Is This Answer Correct ? | 119 Yes | 26 No |
Answer / jaydeep banerjee
IS CODE FOR M20 , M25 , ETC IS IS 456:2000
Is This Answer Correct ? | 100 Yes | 18 No |
Answer / c.p. shrivastava
As per IS the mix of conc. shoud be mix for M20,1:1.5:3
ratio and for M25-1:1:2 ratio by design mix and after 28
days compressive strength not less then 20mpa for M20 &
25mpa for M25
Is This Answer Correct ? | 53 Yes | 9 No |
Why do we provide development length in RCC?
I would like to get the formula How can i calculate the productivity of a mason in terms of brick laying and plaster. i have 6000 Sqmt of interlock laying work i want to calculate - how many masons required to do the job - in how many days can it be done - what will be the production rate in 8 hours shift/ per mason if i can get some excell sheet , it will really help me in my calculations
how to calculate the steel for 450 sft slab, please tell me the solution method
how much brick,cement,and sand required in 1cum brickwork(1:4)
what u mean by M20
9 Answers Srinidhi Constructions,
For removal of formwork of simply supported slab / beam from where to start the deshuttering? ( Max Bending moment of the simply supported beam is in the center hence is it required to start from the supports?)
how can i come to same questions after get answer of one question from table,because if i click for one answer and after get the answer i try to come back on same questions i cant access them the questions change, it break up my link and i jummp here and there so plz tell me the way by which i can back to the same page of questions so can continoue my proper notes thanx
I need old MMUP exam question and answer for Civil engineering
How we decide the depth and size of footing? Give a example?
How much percent dry volume consider for concrete
Mujhe koi ye bta do ki 1.54 hi ku lete h material ki quantity niklne ke liye Sab jgha dhund liya bt samj nhi aaya mujhe koi alag aalag krke smjao ki cement m aggr. Dust m itne % wet or dry % hoti h fir kaise kaise 1.54 aaya kha se aaya smjao koi pls m confuse hu my calling nd wts app no. Is +919034604938
Cemen-1 Fine agr.-2 Core agr.-3 calculate for per 100 qube feet (qubic feet wise)